Rate analysis
Brick edging 7cm wide 11.4 cm deep to plinth protection with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 including grouting with cement mortar 1:4 (1 cement : 4 fine sand).
DSR rate₹59.45per metre
- Item code
- 6.44
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- metre
- Source row
- 1465
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 100m length | |||||
| 9999 | Excavation and disposal of surplus earth | L.S. | 27.3 | ₹2.12 | ₹57.88 |
| 2nd class bricks = 42 nos. + | |||||
| Add wastage @ 10% = 4.2 nos. | |||||
| Total for 10 Nos. = 10x46.2 nos. = 462 Nos. | |||||
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.462 | ₹4,590.00 | ₹2,120.58 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.462 | ₹437.15 | ₹201.96 |
| Cement mortar 1 : 4 (1 cement : 4 fine sand) | |||||
| 3.4 | Rate as per Item Number 3.4 of SH: Mortars | cum | 0.036 | ₹3,713.20 | ₹133.68 |
| LABOUR | |||||
| 0155 | Mason (average) | day | 1 | ₹749.00 | ₹749.00 |
| 0114 | Beldar | day | 1 | ₹645.00 | ₹645.00 |
| 0101 | Bhisti | day | 0.3 | ₹714.00 | ₹214.20 |
| 9999 | Sundries | L.S. | 27.3 | ₹2.12 | ₹57.88 |
Rate build-up
| TOTAL | ₹4,180.18 |
| Add 1 % Water charges on "W" | ₹41.80 |
| TOTAL | ₹4,221.98 |
| Add GST on "X" (multiplying factor 0.2127) | ₹898.02 |
| TOTAL | ₹5,120.00 |
| Add 15% CPOH on "Y" | ₹768.00 |
| TOTAL | ₹5,888.00 |
| Add Cess @ 1% on "Z" | ₹58.88 |
| Cost of 100 metres | ₹5,946.88 |
| Cost of 1 metre | ₹59.47 |
| Say | ₹59.45 |