DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.38 rate analysis

Providing and laying Autoclaved Aerated concrete(AAC) blocks masonry 100 mm/ 125 mm thick with Grade-1 AAC blocks of density 551 to 650 kg/cum conforming to IS:2185 (Part 3) in super structure above plinth level up to floor V level in cement mortar 1:4 (1 cement : 4 coarse sand ). The rate includes providing and placing in position 2 Nos 6 mm dia M.S. bars at every third course of masonry work.

Published rate₹10,195.45per Cum
Rate analysis

Providing and laying Autoclaved Aerated concrete(AAC) blocks masonry 100 mm/ 125 mm thick with Grade-1 AAC blocks of density 551 to 650 kg/cum conforming to IS:2185 (Part 3) in super structure above plinth level up to floor V level in cement mortar 1:4 (1 cement : 4 coarse sand ). The rate includes providing and placing in position 2 Nos 6 mm dia M.S. bars at every third course of masonry work.

DSR rate₹10,195.45per Cum
Item code
6.38
Sub-head
SH 6 · MASONRY WORK
Unit
Cum
Source row
1397

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
8655 Autoclaved aerated concrete (AAC) blocks (grade 1 of density 551 to 650 kg/cum) cum 1 ₹2,915.00 ₹2,915.00
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.15 ₹4,211.70 ₹631.76
2208 Carriage of AAC Blocks cum 1 ₹0.00 ₹0.00
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20
LABOUR
0123 Mason 1st class day 0.36 ₹897.00 ₹322.92
0124 Mason 2nd class day 0.36 ₹816.00 ₹293.76
0115 Coolie day 1.37 ₹736.00 ₹1,008.32
0101 Bhisti day 0.2 ₹816.00 ₹163.20
Reinforcement bars
5.22.1 Rate as per item no. 5.22.1 of SH : Reinforced cement concrete work kg 13.2 ₹107.10 ₹1,413.72
Extra labour element required for lifting of materials (above floor two level upto floor five level)(0.75 x1.5 =1.13).
0115 Coolie day 1.13 ₹736.00 ₹831.68

Rate build-up

TOTAL ₹7,586.56
Add 1 % Water charges on "W-A" ₹61.73
TOTAL ₹7,648.29
Add GST on "X-A" (multiplying factor 0.2127) ₹1,326.09
TOTAL ₹8,974.38
Add 15% CPOH on "Y-A" ₹1,134.10
TOTAL ₹10,108.48
Add Cess @ 1% on "Z-A" ₹86.95
Cost of 1 Cum. ₹10,195.43
Say ₹10,195.45