DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.31.1 rate analysis

Brick work with common burnt clay machine moulded perforated modular bricks of class designation 12.5 conforming to IS : 2222 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand). From ground level upto plinth level

Published rate₹7,032.05per Cum
Rate analysis

Brick work with common burnt clay machine moulded perforated modular bricks of class designation 12.5 conforming to IS : 2222 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand).

DSR rate₹7,032.05per Cum

From ground level upto plinth level

Item code
6.31.1
Sub-head
SH 6 · MASONRY WORK
Unit
Cum
Source row
1117

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
7902 Machine moulded common burnt clay modular perforated bricks of class designation 12.5 1000 Nos 0.487 ₹5,500.00 ₹2,678.50
2201 Carriage of Bricks 1000 Nos 0.487 ₹0.00 ₹0.00
Cement mortar 1 : 6 (1 cement : 6 coarse sand)
3.11 Cement mortar 1 : 6 (1 cement :
6 coarse sand) (Rate as per item No 3.11) cum 0.22 ₹3,541.40 ₹779.11
9999 Sundries i/c steel / wooden strips for making grooves L.S. 16.38 ₹2.27 ₹37.18
LABOUR
0123 Mason 1st class day 0.33 ₹897.00 ₹296.01
0124 Mason 2nd class day 0.33 ₹816.00 ₹269.28
0115 Coolie day 1 ₹736.00 ₹736.00
0101 Bhisti day 0.18 ₹816.00 ₹146.88

Rate build-up

TOTAL ₹4,942.96
Add 1 % Water charges on "W" ₹49.43
TOTAL ₹4,992.39
Add GST on "X" (multiplying factor 0.2127) ₹1,061.88
TOTAL ₹6,054.27
Add 15% CPOH on "Y" ₹908.14
TOTAL ₹6,962.41
Add Cess @ 1% on "Z" ₹69.62
Cost of 1 Cum. ₹7,032.03
Say ₹7,032.05