Rate analysis
Brick work with common burnt clay machine moulded perforated modular bricks of class designation 12.5 conforming to IS : 2222 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand).
DSR rate₹9,005.75per Cum
Above plinth level upto floor V level
- Item code
- 6.31.2
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- Cum
- Source row
- 1117
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 7902 | Machine moulded common burnt clay modular perforated bricks of class designation 12.5 | 1000 Nos | 0.487 | ₹5,500.00 | ₹2,678.50 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.487 | ₹0.00 | ₹0.00 |
| Cement mortar 1 : 6 (1 cement : 6 coarse sand) | |||||
| 3.11 | Rate as per Item Number 3.11 of SH: Mortars | cum | 0.22 | ₹3,541.40 | ₹779.11 |
| 9999 | Sundries i/c steel / wooden strips for making grooves | L.S. | 16.38 | ₹2.27 | ₹37.18 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.44 | ₹897.00 | ₹394.68 |
| 0124 | Mason 2nd class | day | 0.44 | ₹816.00 | ₹359.04 |
| 0115 | Coolie | day | 1.43 | ₹736.00 | ₹1,052.48 |
| 0101 | Bhisti | day | 0.18 | ₹816.00 | ₹146.88 |
| Extra labour for lifting of material (above floor two level up to floor five level) | |||||
| 0115 | Coolie | day | 1.13 | ₹736.00 | ₹831.68 |
| 9999 | Sundries | L.S. | 22.36 | ₹2.27 | ₹50.76 |
Rate build-up
| TOTAL | ₹6,330.31 |
| Add 1 % Water charges on "W" | ₹63.30 |
| TOTAL | ₹6,393.61 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,359.92 |
| TOTAL | ₹7,753.53 |
| Add 15% CPOH on "Y" | ₹1,163.03 |
| TOTAL | ₹8,916.56 |
| Add Cess @ 1% on "Z" | ₹89.17 |
| Cost of 1 Cum. | ₹9,005.73 |
| Say | ₹9,005.75 |