DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.30.2 rate analysis

Above plinth level upto floor V level

Published rate₹9,344.00per Cum
Rate analysis

Above plinth level upto floor V level

DSR rate₹9,344.00per Cum
Item code
6.30.2
Sub-head
SH 6 · MASONRY WORK
Unit
Cum
Source row
1089

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
7901 Machine moulded perforated common burnt clay FPS (non modular) bricks of class designation 12.5 1000 Nos 0.494 ₹5,000.00 ₹2,470.00
2201 Carriage of Bricks 1000 Nos 0.494 ₹0.00 ₹0.00
Cement mortar 1 : 6 (1 cement : 6 coarse sand)
3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.25 ₹3,541.40 ₹885.35
9999 Sundries i/c steel / wooden strips for making grooves L.S. 16.38 ₹2.27 ₹37.18
LABOUR
0123 Mason 1st class day 0.47 ₹897.00 ₹421.59
0124 Mason 2nd class day 0.47 ₹816.00 ₹383.52
0115 Coolie day 1.8 ₹736.00 ₹1,324.80
0101 Bhisti day 0.2 ₹816.00 ₹163.20
Extra labour for lifting of material (above floor two level up to floor five level)
0115 Coolie day 1.13 ₹736.00 ₹831.68
9999 Sundries L.S. 22.36 ₹2.27 ₹50.76

Rate build-up

TOTAL ₹6,568.08
Add 1 % Water charges on "W" ₹65.68
TOTAL ₹6,633.76
Add GST on "X" (multiplying factor 0.2127) ₹1,411.00
TOTAL ₹8,044.76
Add 15% CPOH on "Y" ₹1,206.71
TOTAL ₹9,251.47
Add Cess @ 1% on "Z" ₹92.51
Cost of 1 Cum. ₹9,343.98
Say ₹9,344.00

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook