DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.30.1 rate analysis

From ground level upto plinth level

Published rate₹7,370.30per Cum
Rate analysis

From ground level upto plinth level

DSR rate₹7,370.30per Cum
Item code
6.30.1
Sub-head
SH 6 · MASONRY WORK
Unit
Cum
Source row
1064

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
7901 Machine moulded perforated common burnt clay FPS (non modular) bricks of class designation 12.5 1000 Nos 0.494 ₹5,000.00 ₹2,470.00
2201 Carriage of Bricks 1000 Nos 0.494 ₹0.00 ₹0.00
Cement mortar 1 : 6 (1 cement : 6 coarse sand)
3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.25 ₹3,541.40 ₹885.35
9999 Sundries i/c steel / wooden strips for making grooves L.S. 16.38 ₹2.27 ₹37.18
LABOUR
0123 Mason 1st class day 0.36 ₹897.00 ₹322.92
0124 Mason 2nd class day 0.36 ₹816.00 ₹293.76
0115 Coolie day 1.37 ₹736.00 ₹1,008.32
0101 Bhisti day 0.2 ₹816.00 ₹163.20

Rate build-up

TOTAL ₹5,180.73
Add 1 % Water charges on "W" ₹51.81
TOTAL ₹5,232.54
Add GST on "X" (multiplying factor 0.2127) ₹1,112.96
TOTAL ₹6,345.50
Add 15% CPOH on "Y" ₹951.83
TOTAL ₹7,297.33
Add Cess @ 1% on "Z" ₹72.97
Cost of 1 Cum. ₹7,370.30
Say ₹7,370.30

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook