Rate analysis
Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level.
DSR rate₹1,123.80as per item analysis
Cement mortar 1:4 (1 cement :4 coarse sand)
- Item code
- 6.13.2
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- See analysis
- Source row
- 501
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 sqm. | |||||
| MATERIAL | |||||
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.565 | ₹4,724.00 | ₹2,669.06 |
| Cement mortar 1 : 4 | |||||
| 3.9 | Rate as per Item Number 3.9 of SH: Mortars | cum | 0.28 | ₹4,211.70 | ₹1,179.28 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.565 | ₹0.00 | ₹0.00 |
| 9999 | Sundries & Scaffolding | L.S. | 13.52 | ₹2.27 | ₹30.69 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.6 | ₹897.00 | ₹538.20 |
| 0124 | Mason 2nd class | day | 0.6 | ₹816.00 | ₹489.60 |
| 0115 | Coolie | day | 2 | ₹736.00 | ₹1,472.00 |
| 0101 | Bhisti | day | 0.7 | ₹816.00 | ₹571.20 |
| Extra labour for lifting materials: | |||||
| 0115 | Coolie | day | 1.29 | ₹736.00 | ₹949.44 |
| 10 x 0.115 x 1.13 | |||||
Rate build-up
| TOTAL | ₹7,899.47 |
| Add 1 % Water charges on "W" | ₹78.99 |
| TOTAL | ₹7,978.46 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,697.02 |
| TOTAL | ₹9,675.48 |
| Add 15% CPOH on "Y" | ₹1,451.32 |
| TOTAL | ₹11,126.80 |
| Add Cess @ 1% on "Z" | ₹111.27 |
| Cost for 10 sqm. | ₹11,238.07 |
| Cost for 1 sqm. | ₹1,123.81 |
| Say | ₹1,123.80 |