DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.14 rate analysis

Extra for half brick masonry in superstructure, above floor V level for every four floors or part thereof by mechanical means.

Published rate₹15.00DSR 2023
Rate analysis

Extra for half brick masonry in superstructure, above floor V level for every four floors or part thereof by mechanical means.

DSR rate₹15.00as per item analysis
Item code
6.14
Sub-head
SH 6 · MASONRY WORK
Unit
See analysis
Source row
560

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 59.83 sqm per four floors .
0037 Mobile crane day 0.125 ₹5,050.00 ₹631.25

Rate build-up

TOTAL ₹631.25
Add 1 % Water charges on "W" ₹6.31
TOTAL ₹637.56
Add GST on "X" (multiplying factor 0.2127) ₹135.61
TOTAL ₹773.17
Add 15% CPOH on "Y" ₹115.98
TOTAL ₹889.15
Add Cess @ 1% on "Z" ₹8.89
Cost of 59.83 sqm. ₹898.04
Cost for 1 sqm ₹15.01
Say ₹15.00