Rate analysis
Extra for half brick masonry in superstructure, above floor V level for every four floors or part thereof by mechanical means.
DSR rate₹15.00as per item analysis
- Item code
- 6.14
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- See analysis
- Source row
- 560
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 59.83 sqm per four floors . | |||||
| 0037 | Mobile crane | day | 0.125 | ₹5,050.00 | ₹631.25 |
Rate build-up
| TOTAL | ₹631.25 |
| Add 1 % Water charges on "W" | ₹6.31 |
| TOTAL | ₹637.56 |
| Add GST on "X" (multiplying factor 0.2127) | ₹135.61 |
| TOTAL | ₹773.17 |
| Add 15% CPOH on "Y" | ₹115.98 |
| TOTAL | ₹889.15 |
| Add Cess @ 1% on "Z" | ₹8.89 |
| Cost of 59.83 sqm. | ₹898.04 |
| Cost for 1 sqm | ₹15.01 |
| Say | ₹15.00 |