Rate analysis
Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level.
DSR rate₹1,150.50as per item analysis
Cement mortar 1:3 (1 cement :3 coarse sand)
- Item code
- 6.13.1
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- See analysis
- Source row
- 501
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 sqm. | |||||
| MATERIAL | |||||
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.565 | ₹4,724.00 | ₹2,669.06 |
| Cement mortar 1:3 | |||||
| 3.8 | Rate as per Item Number 3.8 of SH: Mortars | cum | 0.28 | ₹4,881.95 | ₹1,366.95 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.565 | ₹0.00 | ₹0.00 |
| 9999 | Sundries & Scaffolding | L.S. | 13.52 | ₹2.27 | ₹30.69 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.6 | ₹897.00 | ₹538.20 |
| 0124 | Mason 2nd class | day | 0.6 | ₹816.00 | ₹489.60 |
| 0115 | Coolie | day | 2 | ₹736.00 | ₹1,472.00 |
| 0101 | Bhisti | day | 0.7 | ₹816.00 | ₹571.20 |
| Extra labour for lifting materials: | |||||
| 0115 | Coolie | day | 1.29 | ₹736.00 | ₹949.44 |
| 10 x 0.115 x1.13 | |||||
Rate build-up
| TOTAL | ₹8,087.14 |
| Add 1 % Water charges on "W" | ₹80.87 |
| TOTAL | ₹8,168.01 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,737.34 |
| TOTAL | ₹9,905.35 |
| Add 15% CPOH on "Y" | ₹1,485.80 |
| TOTAL | ₹11,391.15 |
| Add Cess @ 1% on "Z" | ₹113.91 |
| Cost for 10 sqm. | ₹11,505.06 |
| Cost for 1 sqm. | ₹1,150.51 |
| Say | ₹1,150.50 |