DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.9.12 rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for Well steining

Published rate₹263.65per sqm
Rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for

DSR rate₹263.65per sqm

Well steining

Item code
5.9.12
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
sqm
Source row
594

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost 26.39 sqm.
Surface area
Outside area = 26.39 sqm
MATERIAL
Assuming that the timber will become unserviceable after being used 8 times
Planks 38 mm (Second class kail wood)
26.39x0.038 = 1.00cum.
Wastage 20% = 0.20cum.
Total = 1.20cum. or 1200 cudm.
Qty for cost using once = 1200/8=150 cudm
1198 Second class kail wood in planks 10 cudm 15 ₹260.00 ₹3,900.00
2nd class kail wood battens
Inside = 2x25x0.50x0.075x0.038 = 0.0712cum.
Outside = 2x28x0.50x0.075x0.038 = 0.0798cum.
Total = 0.1510cum.
Wastage 5% = 0.0076 cum.
Total = 0.1586 cum = 158.60 cudm
Qty for cost using once = 0.1586/8= 0.02 cudm
1197 Second class kail wood in scantling 10 cudm 0.002 ₹260.00 ₹0.52
0302 Safeda ballies 125 mm diameter metre 6.625 ₹44.00 ₹291.50
Inside: 25x1.00 = 25.00m
Outside: 28x1.00 = 28.00m
Total = 53.00m
Qty for cost using once = 53/8 =6.625 m
Add for carriage, labour for erection and dismentalig etc @ 1/6 of cost of material i.e.M ₹698.68

Rate build-up

TOTAL ₹4,192.02
TOTAL ₹4,890.70
Add 1 % Water charges on "W" ₹48.91
TOTAL ₹4,939.61
Add GST on "X" (multiplying factor 0.2127) ₹1,050.66
TOTAL ₹5,990.27
Add 15% CPOH on "Y" ₹898.54
TOTAL ₹6,888.81
Add Cess @ 1% on "Z" ₹68.89
Cost for 26.39sqm. ₹6,957.70
Cost per sqm. ₹263.65
Say ₹263.65

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook