DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.9.13 rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for Vertical and horizontal fins individually or forming box louvers band, facias and eaves boards

Published rate₹1,296.70per sqm
Rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for

DSR rate₹1,296.70per sqm

Vertical and horizontal fins individually or forming box louvers band, facias and eaves boards

Item code
5.9.13
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
sqm
Source row
594

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 239 sqm
Details of cost for 10Nos. Boxes of fins 4 vertical fins 4 metre high and at 1 metre centres, with two horizontal fins all projecting 60cm from face of wall and 5 cm thick.
i.e. 10x[(4x4.00x1.25) + (2x3.00x0.65)] = 239sqm + 5% wastage = 251 sqm.
MATERIAL
1198 Second class kail wood in planks 10 cudm 119.25 ₹260.00 ₹31,005.00
38mm thick-
10x4x4x1.25=200
10x2x3x0.65 =39
Total = 239
Wastage @ 5% = 12
Total = 251sqm.
251x0.038=9.54 cum or 9540 cudm
Qty for cost using once = 9540/8 = 1192.5 cudm
1197 Second class kail wood in scantling 10 cudm 33.625 ₹260.00 ₹8,742.50
10x4x2x5x0.60x0.075x0.050=0.90
10x3x2x5x1.00x0.075x0.050=1.12
10x2x6x0.60x0.075x0.100=0.54 = 2.56 Cum.
Wastage @ 5% =0.13 cum
Total = 2.69 cum= 2690 cudm
Qty for cost using once = 2690/8 = 336.25 cudm
0302 Safeda ballies 125 mm diameter metre 126 ₹44.00 ₹5,544.00
10x2x2x6x4.00 =960m
Wastage @5% = 48m
Total= 1008 m
Qty for cost using once = 1008/8 = 126 m
2204 Carriage of Timber cum 3.075 ₹0.00 ₹0.00
Planks = 9.54
Battens = 2.69
Bailies 1008x3.142x(0.125)²/4= 12.37cum.
Total = 24.60 cum
Qty for cost using once = 24.60/8 = 3.075 cum
LABOUR
For assembling, erection, dismantling and cleaning
0112 Carpenter 2nd class day 110 ₹816.00 ₹89,760.00
0114 Beldar day 110 ₹736.00 ₹80,960.00
9999 Sundries L.S. 807.3 ₹2.27 ₹1,832.57

Rate build-up

TOTAL ₹2,17,844.07
Add 1 % Water charges on "W" ₹2,178.44
TOTAL ₹2,20,022.51
Add GST on "X" (multiplying factor 0.2127) ₹46,798.79
TOTAL ₹2,66,821.30
Add 15% CPOH on "Y" ₹40,023.20
TOTAL ₹3,06,844.50
Add Cess @ 1% on "Z" ₹3,068.45
Cost for 239 sqm. ₹3,09,912.95
Cost per sqm. ₹1,296.71
Say ₹1,296.70