Rate analysis
Centering and shuttering including strutting, propping etc. and removal of form for
DSR rate₹392.15per sqm
Foundations, footings, bases of columns, etc. for mass concrete
- Item code
- 5.9.1
- Sub-head
- SH 5 · REINFORCED CEMENT CONCRETE
- Unit
- sqm
- Source row
- 594
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for footing size 2.5mx2.5mx1.00m | |||||
| Contact area = 10.00 sqm. | |||||
| MATERIAL | |||||
| Assuming shuttering material will become unserviceable after use of 40 times | |||||
| Adding for maintenance @ 10% of cost | |||||
| Taking salvage value after full use of material @ 25% of cost | |||||
| 7319 | Wall form panel 1250x500 mm | each | 0.34 | ₹900.00 | ₹306.00 |
| Qty taken for cost of using once = 16x0.85/40 = 0.34 | |||||
| 7326 | Corner angle 45x45x5 mm 1.50 m long | each | 0.085 | ₹257.00 | ₹21.85 |
| Qty taken for cost of using once = 4x0.85/40 = 0.085 | |||||
| 7327 | 100 mm channel shoulder 2.5 m long | each | 0.17 | ₹950.00 | ₹161.50 |
| Qty taken for cost of using once = 8x0.85/40= 0.17 | |||||
| 7328 | Double clip ( bridge clip) | each | 0.34 | ₹80.00 | ₹27.20 |
| Qty taken for cost of using once = 16x0.85/40 = 0.34 | |||||
| 7329 | Single clip | each | 0.17 | ₹64.00 | ₹10.88 |
| Qty taken for cost of using once = 8x0.85/40 = 0.17 | |||||
| 7330 | M.S. tube 40 mm dia | metre | 0.213 | ₹225.00 | ₹47.93 |
| Qty taken for cost of using once = 10.00x0.85/40 = 0.213 | |||||
| 9999 | Assembly nuts & bolts | L.S. | 22.1 | ₹2.27 | ₹50.17 |
| Qty taken for cost using once = 1040x0.85/40 = 22.10 | |||||
| 9977 | Carriage | L.S. | 78 | ₹2.27 | ₹177.06 |
| LABOUR | |||||
| 0116 | Fitter (grade 1) | day | 0.75 | ₹897.00 | ₹672.75 |
| 0114 | Beldar | day | 1.5 | ₹736.00 | ₹1,104.00 |
| 9999 | Shuttering oil | L.S. | 52 | ₹2.27 | ₹118.04 |
| 9999 | Sundries | L.S. | 26 | ₹2.27 | ₹59.02 |
Rate build-up
| TOTAL | ₹2,756.40 |
| Add 1 % Water charges on "W" | ₹27.56 |
| TOTAL | ₹2,783.96 |
| Add GST on "X" (multiplying factor 0.2127) | ₹592.15 |
| TOTAL | ₹3,376.11 |
| Add 15% CPOH on "Y" | ₹506.42 |
| TOTAL | ₹3,882.53 |
| Add Cess @ 1% on "Z" | ₹38.83 |
| Cost for 10.00 sqm. | ₹3,921.36 |
| Cost per sqm. | ₹392.14 |