Rate analysis
Reinforced cement concrete work in arches, archribs, domes, vaults, shells, folded plate and roofs having slope more than 15° up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).
DSR rate₹12,205.85as per item analysis
- Item code
- 5.5
- Sub-head
- SH 5 · REINFORCED CEMENT CONCRETE
- Unit
- See analysis
- Source row
- 347
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 26.73cum | |||||
| for semicircular arch 6m clear span and 9m long and 30cm thick. | |||||
| Cement concrete 1:1.5:3 = | |||||
| 1x0.50x3.14x6.30x9.00x0.30 = 26.73cum | |||||
| MATERIAL | |||||
| 0295 | Stone Aggregate (Single size) : 20 mm nominal size | cum | 15.236 | ₹1,425.00 | ₹21,711.30 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal size | cum | 7.484 | ₹1,400.00 | ₹10,477.60 |
| 2202 | Carriage of Stone aggregate below 40 mm nominal size | cum | 22.72 | ₹0.00 | ₹0.00 |
| 0982 | Coarse sand (zone III) | cum | 11.36 | ₹1,450.00 | ₹16,472.00 |
| 2203 | Carriage of Coarse sand | cum | 11.36 | ₹0.00 | ₹0.00 |
| 0367 | Portland Cement (0.2833 cum) | tonne | 10.692 | ₹5,156.00 | ₹55,127.95 |
| 2209 | Carriage of Cement | tonne | 10.692 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0155 | Mason (average) | day | 6.42 | ₹857.00 | ₹5,501.94 |
| 0114 | Beldar | day | 73.51 | ₹736.00 | ₹54,103.36 |
| 0101 | Bhisti | day | 24.06 | ₹816.00 | ₹19,632.96 |
| 0002 | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooper | day | 2.14 | ₹900.00 | ₹1,926.00 |
| 0012 | Vibrator(Needle type 40mm) | day | 2.14 | ₹400.00 | ₹856.00 |
| 9999 | Sundries | L.S. | 401.89 | ₹2.27 | ₹912.29 |
| Extra for laying CC over curved surfaces | |||||
| 0123 | Mason 1st class | day | 5 | ₹897.00 | ₹4,485.00 |
| 0124 | Mason 2nd class | day | 5 | ₹816.00 | ₹4,080.00 |
| 0101 | Bhisti | day | 1.5 | ₹816.00 | ₹1,224.00 |
| 0115 | Coolie | day | 4.5 | ₹736.00 | ₹3,312.00 |
| (Extra labour for lifting material upto floor V level : | |||||
| Coolie = 0.75 x 2.0 x 26.73 = 40.10) | |||||
| 0115 | Coolie | day | 40.1 | ₹736.00 | ₹29,513.60 |
Rate build-up
| TOTAL | ₹2,29,336.00 |
| Add 1 % Water charges on "W" | ₹2,293.36 |
| TOTAL | ₹2,31,629.36 |
| Add GST on "X" (multiplying factor 0.2127) | ₹49,267.56 |
| TOTAL | ₹2,80,896.92 |
| Add 15% CPOH on "Y" | ₹42,134.54 |
| TOTAL | ₹3,23,031.46 |
| Add Cess @ 1% on "Z" | ₹3,230.31 |
| Cost for 26.73 cum. | ₹3,26,261.77 |
| Cost for 1 cum. | ₹12,205.83 |
| Say | ₹12,205.85 |