Rate analysis
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.
DSR rate₹107.85per Kg
Thermo-Mechanically Treated bars of grade Fe-500D or more.
- Item code
- 5.22.6
- Sub-head
- SH 5 · REINFORCED CEMENT CONCRETE
- Unit
- Kg
- Source row
- 2376
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 quintal- | |||||
| MATERIAL | |||||
| Deformed twisted steel bars = 1.00 q | |||||
| Wastage 5% = 0.05 q | |||||
| Total =1.05q | |||||
| 1005 | Twisted steel / deformed bars | quintal | 1.05 | ₹5,550.00 | ₹5,827.50 |
| 2205 | Carriage of steel 1.05/10 = 0.105t | tonne | 0.105 | ₹0.00 | ₹0.00 |
| 9999 | Cover block | L.S. | 26 | ₹2.27 | ₹59.02 |
| LABOUR | |||||
| For straightening, cutting, bending, binding and placing in position- | |||||
| 0102 | Blacksmith 1st class | day | 1 | ₹897.00 | ₹897.00 |
| 0114 | Beldar | day | 1 | ₹736.00 | ₹736.00 |
| 9999 | Sundries and binding wire | L.S. | 26.91 | ₹2.27 | ₹61.09 |
Rate build-up
| TOTAL | ₹7,580.61 |
| Add 1 % Water charges on "W" | ₹75.81 |
| TOTAL | ₹7,656.42 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,628.52 |
| TOTAL | ₹9,284.94 |
| Add 15% CPOH on "Y" | ₹1,392.74 |
| TOTAL | ₹10,677.68 |
| Add Cess @ 1% on "Z" | ₹106.78 |
| Cost of one quintal | ₹10,784.46 |
| Cost of 1 Kg. | ₹107.84 |
| Say | ₹107.85 |