DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.22.6 rate analysis

Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more.

Published rate₹107.85per Kg
Rate analysis

Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.

DSR rate₹107.85per Kg

Thermo-Mechanically Treated bars of grade Fe-500D or more.

Item code
5.22.6
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
Kg
Source row
2376

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 quintal-
MATERIAL
Deformed twisted steel bars = 1.00 q
Wastage 5% = 0.05 q
Total =1.05q
1005 Twisted steel / deformed bars quintal 1.05 ₹5,550.00 ₹5,827.50
2205 Carriage of steel 1.05/10 = 0.105t tonne 0.105 ₹0.00 ₹0.00
9999 Cover block L.S. 26 ₹2.27 ₹59.02
LABOUR
For straightening, cutting, bending, binding and placing in position-
0102 Blacksmith 1st class day 1 ₹897.00 ₹897.00
0114 Beldar day 1 ₹736.00 ₹736.00
9999 Sundries and binding wire L.S. 26.91 ₹2.27 ₹61.09

Rate build-up

TOTAL ₹7,580.61
Add 1 % Water charges on "W" ₹75.81
TOTAL ₹7,656.42
Add GST on "X" (multiplying factor 0.2127) ₹1,628.52
TOTAL ₹9,284.94
Add 15% CPOH on "Y" ₹1,392.74
TOTAL ₹10,677.68
Add Cess @ 1% on "Z" ₹106.78
Cost of one quintal ₹10,784.46
Cost of 1 Kg. ₹107.84
Say ₹107.85

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook