Rate analysis
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level.
DSR rate₹107.10per Kg
Mild steel and Medium Tensile steel bars
- Item code
- 5.22A.1
- Sub-head
- SH 5 · REINFORCED CEMENT CONCRETE
- Unit
- Kg
- Source row
- 2539
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 quintal- | |||||
| MATERIAL | |||||
| Mild steel bars = 1.00 q | |||||
| ` | Wastage 5% = 0.05 q | — | — | — | — |
| Total = 1.05 q | |||||
| 1004 | Average rate of Mild steel round bars for reinforcements | quintal | 1.05 | ₹5,500.00 | ₹5,775.00 |
| 2205 | Carriage of Steel NOS/ 10 = 0.105 t | tonne | 0.105 | ₹0.00 | ₹0.00 |
| 9999 | Cover block | L.S. | 26 | ₹2.27 | ₹59.02 |
| LABOUR | |||||
| For straightening, cutting, bending, binding and placing in position- | |||||
| 0102 | Blacksmith 1st class | day | 1 | ₹897.00 | ₹897.00 |
| 0114 | Beldar | day | 1 | ₹736.00 | ₹736.00 |
| 9999 | Sundries and binding wire | L.S. | 26.91 | ₹2.27 | ₹61.09 |
Rate build-up
| TOTAL | ₹7,528.11 |
| Add 1 % Water charges on "W" | ₹75.28 |
| TOTAL | ₹7,603.39 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,617.24 |
| TOTAL | ₹9,220.63 |
| Add 15% CPOH on "Y" | ₹1,383.09 |
| TOTAL | ₹10,603.72 |
| Add Cess @ 1% on "Z" | ₹106.04 |
| Cost of one quintal | ₹10,709.76 |
| Cost of 1 Kg. | ₹107.10 |
| Say | ₹107.10 |