Rate analysis
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.
DSR rate₹102.20per Kg
Hard drawn steel wire fabric
- Item code
- 5.22.5
- Sub-head
- SH 5 · REINFORCED CEMENT CONCRETE
- Unit
- Kg
- Source row
- 2376
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 quintal- | |||||
| MATERIAL | |||||
| Hard drawn steel wire fabric 100kg , 7.75kg | |||||
| per sqm = 12.903 sqm. | |||||
| Add 5% wastage = 0.645 sqm. | |||||
| Total =13.548 sqm | |||||
| 1021 | Hard drawn steel wire fabric | sqm | 13.548 | ₹430.00 | ₹5,825.64 |
| 2205 | Carriage 1.05q = 0.105 tonne | tonne | 0.105 | ₹0.00 | ₹0.00 |
| 9999 | Cover block | L.S. | 26 | ₹2.27 | ₹59.02 |
| LABOUR | |||||
| For cutting and laying in position. | |||||
| 0103 | Blacksmith 2nd class | day | 0.2 | ₹816.00 | ₹163.20 |
| 0114 | Beldar | day | 1.5 | ₹736.00 | ₹1,104.00 |
| 9999 | Sundries and binding wire | L.S. | 13.52 | ₹2.27 | ₹30.69 |
Rate build-up
| TOTAL | ₹7,182.55 |
| Add 1 % Water charges on "W" | ₹71.83 |
| TOTAL | ₹7,254.38 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,543.01 |
| TOTAL | ₹8,797.39 |
| Add 15% CPOH on "Y" | ₹1,319.61 |
| TOTAL | ₹10,117.00 |
| Add Cess @ 1% on "Z" | ₹101.17 |
| Cost of one quintal | ₹10,218.17 |
| Cost of 1 Kg. | ₹102.18 |
| Say | ₹102.20 |