DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.2.2 rate analysis

Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Published rate₹10,852.95DSR 2023
Rate analysis

Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :

DSR rate₹10,852.95as per item analysis

1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item code
5.2.2
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
See analysis
Source row
127

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10x9.18 cum =91.80 cum
MATERIAL
0295 Stone Aggregate (Single size) : 20 mm nominal size cum 52.326 ₹1,425.00 ₹74,564.55
0297 Stone Aggregate (Single size) : 10 mm nominal size cum 25.704 ₹1,400.00 ₹35,985.60
2202 Carriage of Stone aggregate below 40 mm nominal size cum 78.03 ₹0.00 ₹0.00
0982 Coarse sand (zone III) cum 39.015 ₹1,450.00 ₹56,571.75
2203 Carriage of Coarse sand cum 39.015 ₹0.00 ₹0.00
0367 Portland Cement (0.2833 cum) tonne 36.72 ₹5,156.00 ₹1,89,328.32
2209 Carriage of Cement tonne 36.72 ₹0.00 ₹0.00
LABOUR
0114 Beldar day 112.9 ₹736.00 ₹83,094.40
0115 Coolie day 75.3 ₹736.00 ₹55,420.80
0101 Bhisti day 82.6 ₹816.00 ₹67,401.60
0123 Mason 1st class day 9.2 ₹897.00 ₹8,252.40
0124 Mason 2nd class day 9.2 ₹816.00 ₹7,507.20
0002 Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooper day 6.4 ₹900.00 ₹5,760.00
0012 Vibrator(Needle type 40mm) day 6.4 ₹400.00 ₹2,560.00
9999 Sundries L.S. 1,318.2 ₹2.27 ₹2,992.31
9999 Scaffolding L.S. 4,200.3 ₹2.27 ₹9,534.68
Extra labour for lifting of material upto floor V level:
0.75x2.0x91.80 = 137.7
0115 Coolie day 137.7 ₹736.00 ₹1,01,347.20

Rate build-up

TOTAL ₹7,00,320.81
Add 1 % Water charges on "W" ₹7,003.21
TOTAL ₹7,07,324.02
Add GST on "X" (multiplying factor 0.2127) ₹1,50,447.82
TOTAL ₹8,57,771.84
Add 15% CPOH on "Y" ₹1,28,665.78
TOTAL ₹9,86,437.62
Add Cess @ 1% on "Z" ₹9,864.38
Cost for 91.80 cum. ₹9,96,302.00
Cost for 1 cum. ₹10,852.96
Say ₹10,852.95

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook