Rate analysis
Encasing rolled steel section in grillages with cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) including centering and shuttering but, excluding cost of expanded metal and hangers.
DSR rate₹9,663.25per cum
- Item code
- 5.2
- Sub-head
- SH 5 · REINFORCED CEMENT CONCRETE
- Unit
- cum
- Source row
- 2299
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for the grillage 3.50mx3.50mx1.00m = 12.25 cum | |||||
| Cement concrete 1:1½:3 | |||||
| 4.1.2 | Rate as per Item No.4.1.2 of SH: Concrete Work | cum | 12.25 | ₹8,340.85 | ₹1,02,175.41 |
| Extra labour for laying C.C. in RCC work | |||||
| 0114 | Beldar | day | 1.225 | ₹736.00 | ₹901.60 |
| 0101 | Bhisti | day | 2.45 | ₹816.00 | ₹1,999.20 |
| 0123 | Mason 1st class | day | 0.49 | ₹897.00 | ₹439.53 |
| 0124 | Mason 2nd class | day | 0.49 | ₹816.00 | ₹399.84 |
| 0128 | Mate | day | 0.49 | ₹816.00 | ₹399.84 |
| Shuttering : | |||||
| 2(3.50+3.50)x1.00= 14.00 sqm | |||||
| 5.9.5 | Rate as per item 5.9.5 of SH: Reinforced cement concrete work | sqm | 14 | ₹736.40 | ₹10,309.60 |
Rate build-up
| TOTAL | ₹1,16,625.02 |
| Add 1 % Water charges on "W-A" | ₹41.40 |
| TOTAL | ₹1,16,666.42 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹889.39 |
| TOTAL | ₹1,17,555.81 |
| Add 15% CPOH on "Y-A" | ₹760.62 |
| TOTAL | ₹1,18,316.43 |
| Add Cess @ 1% on "Z-A" | ₹58.31 |
| Cost of 12.25 cum. | ₹1,18,374.74 |
| Cost of 1 cum. | ₹9,663.24 |
| Say | ₹9,663.25 |