DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.16 rate analysis

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in shelves, including setting in cement mortar 1:3 (1cement : 3 coarse sand), cost of required centering, shuttering and finishing with neat cement punning on exposed surfaces but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).

Published rate₹20,355.80DSR 2023
Rate analysis

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in shelves, including setting in cement mortar 1:3 (1cement : 3 coarse sand), cost of required centering, shuttering and finishing with neat cement punning on exposed surfaces but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).

DSR rate₹20,355.80as per item analysis
Item code
5.16
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
See analysis
Source row
2043

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 Nos. shelf 0.90x0.45x0.04m thick = 10x0.90x0.45x0.04m = 0.162 cum
Cement concrete 1:1½:3
4.1.2 Rate as per Item No.4.1.2 of SH: Concrete Work cum 0.162 ₹8,340.85 ₹1,351.22
Finishing
13.18 Rate same as per iem no. 13.18 of SH : Finishing sqm 8.5 ₹79.95 ₹679.58
Centring and shuttering:
4.3.1 Rate same as per item no. 4.3.1 of SH : concrete work sqm 1.08 ₹392.15 ₹423.52
Centring and shuttering = 10x2x(0.90+0.45)x0.04 = 1.08 sqm
Extra labour for lifting from FL II upto Floor Level V (Coolie =0.162x0.75x1.50=0.18)
0115 Coolie day 0.18 ₹736.00 ₹132.48
LABOUR
Extra labour for laying cement concrete in RCC work due to delay etc.
0114 Beldar day 0.016 ₹736.00 ₹11.78
0101 Bhisti day 0.032 ₹816.00 ₹26.11
0123 Mason 1st class day 0.006 ₹897.00 ₹5.38
0124 Mason 2nd class day 0.006 ₹816.00 ₹4.90
0128 Mate day 0.006 ₹816.00 ₹4.90
9999 Cement mortar 1:3 for fixing L.S. 44.2 ₹2.27 ₹100.33
9999 Labour for hoisting, Transporting and setting in position L.S. 135.2 ₹2.27 ₹306.90

Rate build-up

TOTAL ₹3,047.10
Add 1 % Water charges on "W-A" ₹5.93
TOTAL ₹3,053.03
Add GST on "X-A" (multiplying factor 0.2127) ₹127.35
TOTAL ₹3,180.38
Add 15% CPOH on "Y-A" ₹108.91
TOTAL ₹3,289.29
Add Cess @ 1% on "Z-A" ₹8.35
Cost for 0.162 cum ₹3,297.64
Cost for 1 cum. ₹20,355.80
Say ₹20,355.80