DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.15 rate analysis

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in lintels, beams and bressumers, including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering and shuttering but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Published rate₹13,899.20DSR 2023
Rate analysis

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in lintels, beams and bressumers, including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering and shuttering but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

DSR rate₹13,899.20as per item analysis
Item code
5.15
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
See analysis
Source row
1971

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for10 Nos. beam 6.60m long 0.50m deep and 0.30m wide = 10x6.60x0.50x0.30 = 9.9 cum.
MATERIAL
Cement concrete 1:1½:3
4.1.2 Rate as per Item No.4.1.2 of SH: Concrete Work cum 9.9 ₹8,340.85 ₹82,574.42
Centring and shuttering
4.3.1 Rate same as per item no. 4.3.1 of SH: Concrete work sqm 69 ₹392.15 ₹27,058.35
Extra labour for lifting above FL II upto Floor Level V (Coolie =9.9x0.75x1.50=11.1)
0115 Coolie day 11.1 ₹736.00 ₹8,169.60
LABOUR
Extra labour for laying cement concrete in RCC work
0114 Beldar day 0.99 ₹736.00 ₹728.64
0.10x9.9
0101 Bhisti day 1.98 ₹816.00 ₹1,615.68
0.20x9.9
0123 Mason 1st class day 0.396 ₹897.00 ₹355.21
0.04x9.9
0124 Mason 2nd class day 0.396 ₹816.00 ₹323.14
0.04x9.9
0128 Mate day 0.396 ₹816.00 ₹323.14
0.04x9.9
9999 Cement mortar 1:3 for fixing L.S. 897 ₹2.27 ₹2,036.19
9999 Labour for hoisting, Transporting and setting in position L.S. 2,691 ₹2.27 ₹6,108.57

Rate build-up

TOTAL ₹1,29,292.94
Add 1 % Water charges on "W-A" ₹196.60
TOTAL ₹1,29,489.54
Add GST on "X-A" (multiplying factor 0.2127) ₹4,223.53
TOTAL ₹1,33,713.07
Add 15% CPOH on "Y-A" ₹3,612.05
TOTAL ₹1,37,325.12
Add Cess @ 1% on "Z-A" ₹276.92
Cost for 9.9 cum ₹1,37,602.04
Cost for 1 cum. ₹13,899.20
Say ₹13,899.20