DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.14 rate analysis

Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc, including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but, excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).

Published rate₹18,234.95DSR 2023
Rate analysis

Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc, including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but, excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).

DSR rate₹18,234.95as per item analysis
Item code
5.14
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
See analysis
Source row
1877

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10x1mx0.20x0.15=0.3 cum
MATERIAL
Cement concrete 1:1½:3
4.1.2 Rate as per Item No.4.1.2 of SH: Concrete Work cum 0.3 ₹8,340.85 ₹2,502.26
Extra labour for lifting above FL II upto FL V
0.3 x 1.5x0.75 = 0.34
0115 Coolie day 0.34 ₹736.00 ₹250.24
9999 Mortar and labour for hoisting and for fixing L.S. 27.3 ₹2.27 ₹61.97
Centring and shuttering
4.3.1 Rate as per Item No.4.3.1 of SH: Concrete Work sqm 3.6 ₹392.15 ₹1,411.74
9999 Add for extra labour for hoisting L.S. 16.1 ₹2.27 ₹36.55
53.82x0.3 = 16.1
LABOUR
Add Extra labour for moulding :
0123 Mason 1st class day 0.174 ₹897.00 ₹156.08
0.58x0.3=0.174
0124 Mason 2nd class day 0.174 ₹816.00 ₹141.98
0.58x0.3=0.174
0115 Coolie day 0.45 ₹736.00 ₹331.20
1.5x0.3=0.450
0101 Bhisti day 0.018 ₹816.00 ₹14.69
0.06x0.3=0.018
Extra labour for laying CC in RCC
0114 Beldar day 0.03 ₹736.00 ₹22.08
0.1x0.3=0.030
0101 Bhisti day 0.06 ₹816.00 ₹48.96
0.2x0.3=0.060
0123 Mason 1st class day 0.012 ₹897.00 ₹10.76
0.04x0.3=0.012
0124 Mason 2nd class day 0.012 ₹816.00 ₹9.79
0.04x0.3=0.012
0128 Mate day 0.012 ₹816.00 ₹9.79
0.04x0.3=0.012

Rate build-up

TOTAL ₹5,008.09
Add 1 % Water charges on "W-A" ₹10.94
TOTAL ₹5,019.03
Add GST on "X-A" (multiplying factor 0.2127) ₹235.04
TOTAL ₹5,254.07
Add 15% CPOH on "Y-A" ₹201.01
TOTAL ₹5,455.08
Add Cess @ 1% on "Z-A" ₹15.41
Cost for 0.3 cum ₹5,470.49
Cost for 1 cum. ₹18,234.97
Say ₹18,234.95