Rate analysis
Providing, hoisting and fixing up to floor five level precast reinforced cement concrete in small lintels not exceeding 1.5m clear span up to floor five level, including the cost of required centering, shuttering but , excluding the cost of reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).
DSR rate₹14,325.95per cum
- Item code
- 5.13
- Sub-head
- SH 5 · REINFORCED CEMENT CONCRETE
- Unit
- cum
- Source row
- 1786
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for a lintel : | |||||
| Qty = 0.054 cum | |||||
| MATERIAL | |||||
| 1.5m clear span = 1.8x0.20x0.15 = 0.054 cum. | |||||
| Cement Concrete 1:1½:3 | |||||
| 4.1.2 | Rate as per Item No.4.1.2 of SH: Concrete Work | cum | 0.054 | ₹8,340.85 | ₹450.41 |
| Extra labour for lifting material above FLII upto floor V level =0.054x 0.75 x 1.50 = 0.061 ( for precast concrete) | |||||
| 0115 | Coolie | day | 0.061 | ₹736.00 | ₹44.90 |
| Centring and shuttering | |||||
| 4.3.1 | Rate as per item no. 4.3.1 of SH: Concrete work | sqm | 0.6 | ₹392.15 | ₹235.29 |
| Extra labour for laying CC in RCC work | |||||
| 0114 | Beldar | day | 0.005 | ₹736.00 | ₹3.68 |
| 0101 | Bhisti | day | 0.01 | ₹816.00 | ₹8.16 |
| 0123 | Mason 1st class | day | 0.002 | ₹897.00 | ₹1.79 |
| 0124 | Mason 2nd class | day | 0.002 | ₹816.00 | ₹1.63 |
| 0128 | Mate | day | 0.002 | ₹816.00 | ₹1.63 |
Rate build-up
| TOTAL | ₹747.49 |
| Add 1 % Water charges on "W-A" | ₹0.62 |
| TOTAL | ₹748.11 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹13.27 |
| TOTAL | ₹761.38 |
| Add 15% CPOH on "Y-A" | ₹11.35 |
| TOTAL | ₹772.73 |
| Add Cess @ 1% on "Z-A" | ₹0.87 |
| Cost for 0.054 cum. | ₹773.60 |
| Cost per cum | ₹14,325.93 |
| Say | ₹14,325.95 |