Rate analysis
Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but , excluding cost of reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).
DSR rate₹10,585.90as per item analysis
- Item code
- 5.12
- Sub-head
- SH 5 · REINFORCED CEMENT CONCRETE
- Unit
- See analysis
- Source row
- 1685
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| Cement concrete 1:1½:3 in string or lacing course etc | |||||
| 4.5.1 | Rate as per Item No.4.5.1 of SH:CONCRETE WORK | cum | 1 | ₹10,105.10 | ₹10,105.10 |
| (NB : Rate has been taken including cost of fixing in CM 1:2 as precast members are to be fixesd in CM 1:2)(1 cement : 2 coarse sand) as per CPWD specifications) | |||||
| LABOUR | |||||
| Extra labour for laying CC in RCC work | |||||
| 0114 | Beldar | day | 0.1 | ₹736.00 | ₹73.60 |
| 0101 | Bhisti | day | 0.2 | ₹816.00 | ₹163.20 |
| 0123 | Mason 1st class | day | 0.04 | ₹897.00 | ₹35.88 |
| 0124 | Mason 2nd class | day | 0.04 | ₹816.00 | ₹32.64 |
| 0128 | Mate | day | 0.04 | ₹816.00 | ₹32.64 |
Rate build-up
| TOTAL | ₹10,443.06 |
| Add 1 % Water charges on "W-A" | ₹3.38 |
| TOTAL | ₹10,446.44 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹72.60 |
| TOTAL | ₹10,519.04 |
| Add 15% CPOH on "Y-A" | ₹62.09 |
| TOTAL | ₹10,581.13 |
| Add Cess @ 1% on "Z-A" | ₹4.76 |
| Cost for 1 cum. | ₹10,585.89 |
| Say | ₹10,585.90 |