Providing and fixing up to floor five level precast cement concrete solid block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete :
1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including (Recycled Concrete Aggregate (RCA) upto 25%)).
Published rate₹17,677.25per cum
Rate analysis
Providing and fixing up to floor five level precast cement concrete solid block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete :
DSR rate₹17,677.25per cum
1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including (Recycled Concrete Aggregate (RCA) upto 25%)).
Item code
4.7.1A
Sub-head
SH 4 · CONCRETE WORK
Unit
cum
Source row
1241
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for 250 no blocks, 40x20x30cm
250 no x 0.40m x 0.30m x 0.20m = 6 cum
MATERIAL
Cement concrete 1:1.5:3
4.1.2A
Rate as per Item No.4.1.2A of SH:CONCRETE WORK
cum
6
₹8,127.80
₹48,766.80
Centering and shuttering
(1) Mould
(i) Plate 3mm thick
10x0.28 sqm. @ 23.55kg/m² = 65.9 kg.
(ii) Flat 10x5mm
Handle
10x2x0.25 x0.4 = 2kg. Total =67.9 kg
Assuming shuttering will become unserviceable after use of 40 times and taking 75% credit.
Qty taken for cost of using once = 67.9x0.75/40 = 1.273 kg
10.1
Rate as per item no.10.1 S.H: steel work
kg
1.273
₹117.35
₹149.39
(2) Moulding Platform
Assuming platform will become unserviceable after use of 40 times.
(i) Brick on edge flooring cement mortar 1:6
10x1x2.0x2.0m = 40 sqm.
Qty taken for cost of using once = 40/40 = 1 sqm
11.1.2
Rate as per item no. 11.1.2 S.H.: Flooring work.
sqm
1
₹965.55
₹965.55
(ii) 25mm thick cement concrete 1:2:4 in pavement
10x2.00x2.00x0.025 = 1
Qty taken for cost of using once = 1/40 = 0.025 cum
Sub A/R-1
Rate as per item no. Sub AR-1 (Reference item no 11.7)
cum
0.025
₹8,844.45
₹221.11
Mortar 1:3 for Fixing
10x0.202/100x25=0.51
3.8
Rate as per Item No 3.8
cum
0.51
₹4,881.95
₹2,489.79
Extra Labour for lifting (6x0.75x1.5=6.75)
0115
Coolie
day
6.75
₹736.00
₹4,968.00
Labour for hoisting and setting in position
0123
Mason (brick layer) 1st class
day
6
₹897.00
₹5,382.00
0114
Beldar
day
36
₹736.00
₹26,496.00
Rate build-up
TOTAL
₹89,438.64
Add 1 % Water charges on "W-A"
₹393.36
TOTAL
₹89,832.00
Add GST on "X-A" (multiplying factor 0.2127)
₹8,450.39
TOTAL
₹98,282.39
Add 15% CPOH on "Y-A"
₹7,226.93
TOTAL
₹1,05,509.32
Add Cess @ 1% on "Z-A"
₹554.06
Cost for 6 cum.
₹1,06,063.38
Cost per cum.
₹17,677.23
Say
₹17,677.25
Use this rate in the interactive workbook