DSR 2023 · SH 4 · CONCRETE WORK

CPWD DSR item 4.7.1 rate analysis

Providing and fixing up to floor five level precast cement concrete solid block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete : 1:1½:3 (1 Cement: 1½ coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).

Published rate₹17,889.25per cum
Rate analysis

Providing and fixing up to floor five level precast cement concrete solid block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete :

DSR rate₹17,889.25per cum

1:1½:3 (1 Cement: 1½ coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).

Item code
4.7.1
Sub-head
SH 4 · CONCRETE WORK
Unit
cum
Source row
1241

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 250 no blocks, 40x20x30cm
250 no x 0.40m x 0.30m x 0.20m = 6 cum
MATERIAL
Cement concrete 1:1.5:3
4.1.2 Rate as per Item No.4.1.2 of SH:CONCRETE WORK cum 6 ₹8,340.85 ₹50,045.10
Centering and shuttering
(1) Mould
(i) Plate 3mm thick
10x0.28 sqm. @ 23.55kg/m² = 65.9 kg.
(ii) Flat 10x5mm
Handle
10x2x0.25 x0.4 = 2kg. Total =67.9 kg
Assuming shuttering will become unserviceable after use of 40 times and taking 75% credit.
Qty taken for cost of using once = 67.9x0.75/40 = 1.273 kg
10.1 Rate as per item no.10.1 S.H: steel work kg 1.273 ₹117.35 ₹149.39
(2) Moulding Platform
Assuming platform will become unserviceable after use of 40 times.
(i) Brick on edge flooring cement mortar 1:6
10x1x2.0x2.0m = 40 sqm.
Qty taken for cost of using once = 40/40 = 1 sqm
11.1.2 Rate as per item no. 11.1.2 S.H.: Flooring work. sqm 1 ₹965.55 ₹965.55
(ii) 25mm thick cement concrete 1:2:4 in pavement
10x2.00x2.00x0.025 = 1
Qty taken for cost of using once = 1/40 = 0.025 cum
11.7 Rate as per Item Number 11.7 of SH:Flooring cum 0.025 ₹8,595.15 ₹214.88
Mortar 1:3 for Fixing
10x0.202/100x25=0.51
3.8 Rate as per Item No 3.8 cum 0.51 ₹4,881.95 ₹2,489.79
Extra Labour for lifting (6x0.75x1.5=6.75)
0115 Coolie day 6.75 ₹736.00 ₹4,968.00
Labour for hoisting and setting in position
0123 Mason (brick layer) 1st class day 6 ₹897.00 ₹5,382.00
0114 Beldar day 36 ₹736.00 ₹26,496.00

Rate build-up

TOTAL ₹90,710.71
Add 1 % Water charges on "W-A" ₹393.36
TOTAL ₹91,104.07
Add GST on "X-A" (multiplying factor 0.2127) ₹8,450.39
TOTAL ₹99,554.46
Add 15% CPOH on "Y-A" ₹7,226.93
TOTAL ₹1,06,781.39
Add Cess @ 1% on "Z-A" ₹554.06
Cost for 6 cum. ₹1,07,335.45
Cost per cum. ₹17,889.24
Say ₹17,889.25