Rate analysis
Providing and fixing up to floor five level precast cement concrete hollow block, including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering complete.
DSR rate₹14,624.20per cum
1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) .
- Item code
- 4.8.1
- Sub-head
- SH 4 · CONCRETE WORK
- Unit
- cum
- Source row
- 1336
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for one block of overall size | |||||
| 1m x 0.50m and 0.10m thick having 6 vertical hollows, 40x20x30cm finished contents = 1mx0.5mx0.1m = 0.05cum | |||||
| MATERIAL | |||||
| Cement concrete 1:1.5:3 | |||||
| Net qty = 0.05[6x0.5x{2x1/2(0.05+7)}x0.074] = 0.023cum | |||||
| 4.1.2 | Rate as per Item No.4.1.2 of SH:CONCRETE WORK | cum | 0.023 | ₹8,340.85 | ₹191.84 |
| 9999 | Centering and shuttering including T&P charges, hire charges of steel mould, table vibrator, rammer, bolts nuts & washers etc. | L.S. | 26.91 | ₹2.27 | ₹61.09 |
| Cement mortar 1:2 for fixing | |||||
| 3.7 | Rate as per Item No.3.7 of SH:MORTARS | cum | 0.002 | ₹5,584.50 | ₹11.17 |
| LABOUR | |||||
| Extra Labour for lifting material upto floor V level | |||||
| 0115 | Coolie | day | 0.056 | ₹736.00 | ₹41.22 |
| Labour for hoisting and setting in position | |||||
| 0123 | Mason (brick layer) 1st class | day | 0.05 | ₹897.00 | ₹44.85 |
| 0114 | Beldar | day | 0.3 | ₹736.00 | ₹220.80 |
Rate build-up
| TOTAL | ₹570.97 |
| Add 1 % Water charges on "W-A" | ₹3.79 |
| TOTAL | ₹574.76 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹81.45 |
| TOTAL | ₹656.21 |
| Add 15% CPOH on "Y-A" | ₹69.66 |
| TOTAL | ₹725.87 |
| Add Cess @ 1% on "Z-A" | ₹5.34 |
| Cost for 0.05 cum. | ₹731.21 |
| Cost per cum. | ₹14,624.20 |
| Say | ₹14,624.20 |