Rate analysis
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
DSR rate₹7,878.50per cum
1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
- Item code
- 4.1.3
- Sub-head
- SH 4 · CONCRETE WORK
- Unit
- cum
- Source row
- 4
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 0295 | Stone Aggregate (Single size) : 20 mm nominal size | cum | 0.67 | ₹1,425.00 | ₹954.75 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal size | cum | 0.22 | ₹1,400.00 | ₹308.00 |
| 2202 | Carriage of Stone aggregate below 40 mm nominal size | cum | 0.89 | ₹0.00 | ₹0.00 |
| 0982 | Coarse sand (zone III) | cum | 0.445 | ₹1,450.00 | ₹645.25 |
| 2203 | Carriage of Coarse sand | cum | 0.445 | ₹0.00 | ₹0.00 |
| 0367 | Portland Cement (0.2225 cum) | tonne | 0.32 | ₹5,156.00 | ₹1,649.92 |
| 2209 | Carriage of Cement | tonne | 0.32 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0155 | Mason (average) | day | 0.1 | ₹857.00 | ₹85.70 |
| 0114 | Beldar | day | 1.63 | ₹736.00 | ₹1,199.68 |
| 0101 | Bhisti | day | 0.7 | ₹816.00 | ₹571.20 |
| 0002 | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooper | day | 0.07 | ₹900.00 | ₹63.00 |
| 0012 | Vibrator(Needle type 40mm) | day | 0.07 | ₹400.00 | ₹28.00 |
| 9999 | Sundries | L.S. | 14.3 | ₹2.27 | ₹32.46 |
Rate build-up
| TOTAL | ₹5,537.96 |
| Add 1 % Water charges on "W" | ₹55.38 |
| TOTAL | ₹5,593.34 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,189.70 |
| TOTAL | ₹6,783.04 |
| Add 15% CPOH on "Y" | ₹1,017.46 |
| TOTAL | ₹7,800.50 |
| Add Cess @ 1% on "Z" | ₹78.00 |
| Cost of 1 cum. | ₹7,878.50 |
| Say | ₹7,878.50 |