Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge. Bi Axial Woven polyster geogrid of minimum tensile strength 40KN/m in both Longitudinal and Transverse direction.

Published rate₹329.70per sqm
Rate analysis

Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.

DSR rate₹329.70per sqm

Bi Axial Woven polyster geogrid of minimum tensile strength 40KN/m in both Longitudinal and Transverse direction.

Item code
26.85.2
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
4534

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of Cost for 300 Sqm.
MATERIALS:
8989 Bi Axial Woven polyster geogrid of minimume tensile strength 40KN/m in both Longitudinal and Transverse direction. sqm 300 ₹198.00 ₹59,400.00
Add 5 percent of the cost of reinforcing elements geogrid for wastage and accessories like tie-strips, nuts and bolts and loops/lungs for joining reinforcing elements with the facia panels, overlaps and other protective elements for geogrid and all other activities required to complete the item  in all respect including transportation.i.e 5% of (P) ₹2,970.00
LABOUR:
0128 Mate day 0.36 ₹816.00 ₹293.76
0114 Beldar day 6 ₹736.00 ₹4,416.00
0139 Skilled Beldar day 3 ₹816.00 ₹2,448.00

Rate build-up

Total ₹69,527.76
Add 1 % Water charges on "W" ₹695.28
TOTAL ₹70,223.04
Add GST on "X" (multiplying factor 0.2127) ₹14,936.44
TOTAL ₹85,159.48
Add 15% CPOH on "Y" ₹12,773.92
TOTAL ₹97,933.40
Add Cess @ 1% on "Z" ₹979.33
Cost of 300 sqm ₹98,912.73
Cost of 1 sqm ₹329.71
Say ₹329.70