Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.
Bi Axial Woven polyster geogrid of minimum tensile strength 20KN/m in both Longitudinal and Transverse direction.
Published rate₹229.65per sqm
Rate analysis
Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.
DSR rate₹229.65per sqm
Bi Axial Woven polyster geogrid of minimum tensile strength 20KN/m in both Longitudinal and Transverse direction.
Item code
26.85.1
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
4534
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of Cost for 300 Sqm.
MATERIALS:
8988
Bi Axial Woven polyster geogrid of minimum tensile strength 20KN/m in both Longitudinal and Transverse direction.
sqm
300
₹131.00
₹39,300.00
—
Add 5 percent of the cost of reinforcing elements geogrid for wastage and accessories like tie-strips, nuts and bolts and loops/lungs for joining reinforcing elements with the facia panels, overlaps and other protective elements for geogrid and all other activities required to complete the item in all respect including transportation.i.e 5% of (P)
—
—
—
₹1,965.00
LABOUR:
0128
Mate
day
0.36
₹816.00
₹293.76
0114
Beldar
day
6
₹736.00
₹4,416.00
0139
Skilled Beldar
day
3
₹816.00
₹2,448.00
Rate build-up
Total
₹48,422.76
Add 1 % Water charges on "W"
₹484.23
TOTAL
₹48,906.99
Add GST on "X" (multiplying factor 0.2127)
₹10,402.52
TOTAL
₹59,309.51
Add 15% CPOH on "Y"
₹8,896.43
TOTAL
₹68,205.94
Add Cess @ 1% on "Z"
₹682.06
Cost of 300 sqm
₹68,888.00
Cost of 1 sqm
₹229.63
Say
₹229.65
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.