Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge. Bi Axial Woven polyster geogrid of minimum tensile strength 20KN/m in both Longitudinal and Transverse direction.

Published rate₹229.65per sqm
Rate analysis

Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.

DSR rate₹229.65per sqm

Bi Axial Woven polyster geogrid of minimum tensile strength 20KN/m in both Longitudinal and Transverse direction.

Item code
26.85.1
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
4534

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of Cost for 300 Sqm.
MATERIALS:
8988 Bi Axial Woven polyster geogrid of minimum tensile strength 20KN/m in both Longitudinal and Transverse direction. sqm 300 ₹131.00 ₹39,300.00
Add 5 percent of the cost of reinforcing elements geogrid for wastage and accessories like tie-strips, nuts and bolts and loops/lungs for joining reinforcing elements with the facia panels, overlaps and other protective elements for geogrid and all other activities required to complete the item  in all respect including transportation.i.e 5% of (P) ₹1,965.00
LABOUR:
0128 Mate day 0.36 ₹816.00 ₹293.76
0114 Beldar day 6 ₹736.00 ₹4,416.00
0139 Skilled Beldar day 3 ₹816.00 ₹2,448.00

Rate build-up

Total ₹48,422.76
Add 1 % Water charges on "W" ₹484.23
TOTAL ₹48,906.99
Add GST on "X" (multiplying factor 0.2127) ₹10,402.52
TOTAL ₹59,309.51
Add 15% CPOH on "Y" ₹8,896.43
TOTAL ₹68,205.94
Add Cess @ 1% on "Z" ₹682.06
Cost of 300 sqm ₹68,888.00
Cost of 1 sqm ₹229.63
Say ₹229.65