DSR 2023 · SH 26 · NEW TECHNOLOGIES AND

CPWD DSR item 26.85.3 rate analysis

Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge. Bi Axial Woven polyster geogrid of minimum tensile strength 60KN/m in both Longitudinal and Transverse direction.

Published rate₹416.35per sqm
Rate analysis

Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.

DSR rate₹416.35per sqm

Bi Axial Woven polyster geogrid of minimum tensile strength 60KN/m in both Longitudinal and Transverse direction.

Item code
26.85.3
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
4534

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of Cost for 300 Sqm.
MATERIALS:
8990 Bi Axial Woven polyster geogrid of minimum tensile strength 60KN/m in both Longitudinal and Transverse direction. sqm 300 ₹256.00 ₹76,800.00
Add 5 percent of the cost of reinforcing elements geogrid for wastage and accessories like tie-strips, nuts and bolts and loops/lungs for joining reinforcing elements with the facia panels, overlaps and other protective elements for geogrid and all other activities required to complete the item  in all respect including transportation.i.e 5% of (P) ₹3,840.00
LABOUR:
0128 Mate day 0.36 ₹816.00 ₹293.76
0114 Beldar day 6 ₹736.00 ₹4,416.00
0139 Skilled Beldar day 3 ₹816.00 ₹2,448.00

Rate build-up

Total ₹87,797.76
Add 1 % Water charges on "W" ₹877.98
TOTAL ₹88,675.74
Add GST on "X" (multiplying factor 0.2127) ₹18,861.33
TOTAL ₹1,07,537.07
Add 15% CPOH on "Y" ₹16,130.56
TOTAL ₹1,23,667.63
Add Cess @ 1% on "Z" ₹1,236.68
Cost of 300 sqm ₹1,24,904.31
Cost of 1 sqm ₹416.35
Say ₹416.35