CPWD DSR item 26.84.1 rate analysis

Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge. Uni Axial Woven polyster geogrid of minimum tensile strength 40KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction.

Published rate₹271.45per sqm
Rate analysis

Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.

DSR rate₹271.45per sqm

Uni Axial Woven polyster geogrid of minimum tensile strength 40KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction.

Item code
26.84.1
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
4335

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of Cost for 300 Sqm.
MATERIALS:
8979 Uni Axial Woven polyster geogrid of minimum tensile strength 40KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction. sqm 300 ₹159.00 ₹47,700.00
Add 5 percent of the cost of reinforcing elements geogrid for wastage and accessories like tie-strips, nuts and bolts and loops/lungs for joining reinforcing elements with the facia panels, overlaps and other protective elements for geogrid and all other activities required to complete the item in all respect including transportation. i.e 5% of (P) ₹2,385.00
LABOUR:
0128 Mate day 0.36 ₹816.00 ₹293.76
0114 Beldar day 6 ₹736.00 ₹4,416.00
0139 Skilled Beldar day 3 ₹816.00 ₹2,448.00

Rate build-up

Total ₹57,242.76
Add 1 % Water charges on "W" ₹572.43
TOTAL ₹57,815.19
Add GST on "X" (multiplying factor 0.2127) ₹12,297.29
TOTAL ₹70,112.48
Add 15% CPOH on "Y" ₹10,516.87
TOTAL ₹80,629.35
Add Cess @ 1% on "Z" ₹806.29
Cost of 300 sqm ₹81,435.64
Cost of 1 sqm ₹271.45
Say ₹271.45