DSR 2023 · SH 26 · NEW TECHNOLOGIES AND

CPWD DSR item 26.84.2 rate analysis

Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge. Uni Axial Woven polyster geogrid of minimum tensile strength 60KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction.

Published rate₹310.30per sqm
Rate analysis

Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.

DSR rate₹310.30per sqm

Uni Axial Woven polyster geogrid of minimum tensile strength 60KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction.

Item code
26.84.2
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
4335

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of Cost for 300 Sqm.
MATERIALS:
8980 Uni Axial Woven polyster geogrid of minimum tensile strength 60KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction. sqm 300 ₹185.00 ₹55,500.00
Add 5 percent of the cost of reinforcing elements geogrid for wastage and accessories like tie-strips, nuts and bolts and loops/lungs for joining reinforcing elements with the facia panels, overlaps and other protective elements for geogrid and all other activities required to complete the item  in all respect including transportation.i.e 5% of (P) ₹2,775.00
LABOUR:
0128 Mate day 0.36 ₹816.00 ₹293.76
0114 Beldar day 6 ₹736.00 ₹4,416.00
0139 Skilled Beldar day 3 ₹816.00 ₹2,448.00

Rate build-up

Total ₹65,432.76
Add 1 % Water charges on "W" ₹654.33
TOTAL ₹66,087.09
Add GST on "X" (multiplying factor 0.2127) ₹14,056.72
TOTAL ₹80,143.81
Add 15% CPOH on "Y" ₹12,021.57
TOTAL ₹92,165.38
Add Cess @ 1% on "Z" ₹921.65
Cost of 300 sqm ₹93,087.03
Cost of 1 sqm ₹310.29
Say ₹310.30