Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.
Uni Axial Woven polyster geogrid of minimum tensile strength 60KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction.
Published rate₹310.30per sqm
Rate analysis
Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.
DSR rate₹310.30per sqm
Uni Axial Woven polyster geogrid of minimum tensile strength 60KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction.
Item code
26.84.2
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
4335
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of Cost for 300 Sqm.
MATERIALS:
8980
Uni Axial Woven polyster geogrid of minimum tensile strength 60KN/m in the Longitudinal direction and 20 KN/m in the Transverse direction.
sqm
300
₹185.00
₹55,500.00
—
Add 5 percent of the cost of reinforcing elements geogrid for wastage and accessories like tie-strips, nuts and bolts and loops/lungs for joining reinforcing elements with the facia panels, overlaps and other protective elements for geogrid and all other activities required to complete the item in all respect including transportation.i.e 5% of (P)
—
—
—
₹2,775.00
LABOUR:
0128
Mate
day
0.36
₹816.00
₹293.76
0114
Beldar
day
6
₹736.00
₹4,416.00
0139
Skilled Beldar
day
3
₹816.00
₹2,448.00
Rate build-up
Total
₹65,432.76
Add 1 % Water charges on "W"
₹654.33
TOTAL
₹66,087.09
Add GST on "X" (multiplying factor 0.2127)
₹14,056.72
TOTAL
₹80,143.81
Add 15% CPOH on "Y"
₹12,021.57
TOTAL
₹92,165.38
Add Cess @ 1% on "Z"
₹921.65
Cost of 300 sqm
₹93,087.03
Cost of 1 sqm
₹310.29
Say
₹310.30
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.