Rate analysis
Supplying and fixing 10 Gauge weld mesh of size 100mm x100 mm for floor/roof slab concrete screed over the micro beams as reinforcement. The weld mesh shall be fixed as per drawing.
DSR rate₹254.75per sqm
- Item code
- 26.55
- Sub-head
- SH 26 · NEW TECHNOLOGIES AND
- Unit
- sqm
- Source row
- 2824
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 9sqm (3mx3m) | |||||
| MATERIAL | |||||
| Mesh area = 9.00sqm, Add wastage @ 5% = 0.45sqm, Total area = 9.45 sqm | |||||
| 1223 | Steel weld mesh | sqm | 9.45 | ₹150.00 | ₹1,417.50 |
| Labour for filling the quarry dust | |||||
| 0103 | Blacksmith 2nd class | day | 0.125 | ₹816.00 | ₹102.00 |
| 0114 | Beldar | day | 0.125 | ₹736.00 | ₹92.00 |
Rate build-up
| TOTAL | ₹1,611.50 |
| Add 1% water charges | ₹16.12 |
| TOTAL | ₹1,627.62 |
| Add GST on "X" (multiplying factor 0.2127) | ₹346.19 |
| TOTAL | ₹1,973.81 |
| Add 15% CPOH on "Y" | ₹296.07 |
| TOTAL | ₹2,269.88 |
| Add Cess @1% on "Z" | ₹22.70 |
| Cost of 9 sqm | ₹2,292.58 |
| Cost of 1 sqm | ₹254.73 |
| Say | ₹254.75 |