Rate analysis
Application of ZMB 60/equivalent solution (100 Kg ZMB 60/equivalent, 1 litre ZMB Nano Thinner, 20 litre water & 1 Litre Zycoprime/equivalent = 122 litre/kg) over already applied coat of Zycosil/equivalent & Zycoprime/equivalent solution on the top of all the RCC plinth beams by brush/spray coat before erection of GFRG over RCC plinth beams in GF. In the case of upper floors 150 mm wide on floor slab for all the external walls, bath/toilet/wet areas (3 hrs drying time) before erection of wall panel on upper floors including erection of parapet wall.
DSR rate₹371.25per sqm
- Item code
- 26.56
- Sub-head
- SH 26 · NEW TECHNOLOGIES AND
- Unit
- sqm
- Source row
- 2845
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 122sqm | |||||
| MATERIAL | |||||
| 8516 | ZMB 60 / equivalent | kg | 100 | ₹130.00 | ₹13,000.00 |
| 8517 | ZMB Thinner | litre | 1 | ₹250.00 | ₹250.00 |
| 8518 | Zycoprime / equivalent | litre | 1 | ₹170.00 | ₹170.00 |
| 9999 | Water, brush, technical supervision etc. | L.S. | 78 | ₹2.27 | ₹177.06 |
| LABOUR | |||||
| 0123 | Mason (Brick layer) 1st class | day | 20.333 | ₹897.00 | ₹18,238.70 |
Rate build-up
| TOTAL | ₹31,835.76 |
| Add 1% water charges | ₹318.36 |
| TOTAL | ₹32,154.12 |
| Add GST on "X" (multiplying factor 0.2127) | ₹6,839.18 |
| TOTAL | ₹38,993.30 |
| Add 15% CPOH on "Y" | ₹5,849.00 |
| TOTAL | ₹44,842.30 |
| Add Cess @1% on "Z" | ₹448.42 |
| Cost of 122 sqm | ₹45,290.72 |
| Cost of 1 sqm | ₹371.24 |
| Say | ₹371.25 |