Laying of GFRG panel as roof / floor slab panel and staircase panel using suitable crane as per instructions of Engineer-in-Charge, including providing support system with 25mm x 300mm-400 mm wide plywood, as runner with proper prop below proposed micro beams including
(a) Cutting of top flange of panel to 180 mm wide (leaving 25mm projection on either side) to provide RCC embedded micro beam as per cutting drawings and structural drawings.
(b) Reinforcement for micro beams and tie beams to be provided in position with proper anchorage as per structural drawings.
(c) Provision for Electrical cabling, fan hooks and laying of pipes for plumbing work.
(d) Concreting of Tie beam, micro beam and top of GFRG panels (50 mm thick) with M-25 cement concrete mix using coarse aggregate of size less than 20 mm including laying of 10 gauge 100x100 size weld mesh with 25 mm effective cover from the panel top.
- Item code
- 26.54
- Sub-head
- SH 26 · NEW TECHNOLOGIES AND
- Unit
- sqm
- Source row
- 2800
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 9 sqm (3mx3m wall panel) | |||||
| LABOUR | |||||
| Providing runner & support system in place for placing panel in position with 40mm bearing on walls( 4 Skilled persons for 1/2 Hrs /1/16 days) | |||||
| 0123 | Mason (Brick layer) 1st class | day | 0.25 | ₹897.00 | ₹224.25 |
| Lifting panel from stack by crane and placing in position with 40 mm bearing on walls 4 skilled labour for 1 hrs | |||||
| 0123 | Mason (Brick layer) 1st class | day | 0.5 | ₹897.00 | ₹448.50 |
| Cutting & removal of top flange to protruding 25mm on either sides for keying panel into RCC micro beams in position (every 3rd cavities runner/span in place beneath) and providing concealed beam reinforcement in position, side shuttering for slab for external side(with 6mm grove) also to be provided (mean while providing fan hooks, electrical cabling, piping etc by coordinate task by concerned skilled persons, 4 skilled labour for 1 hrs | |||||
| 0123 | Mason (Brick layer) 1st class | day | 0.5 | ₹897.00 | ₹448.50 |
| 9999 | Hire charges for runner and support system and side shuttering for external side of slab for 5 days | L.S. | 29 | ₹2.27 | ₹65.83 |
| 0037 | Mobile crane | day | 0.125 | ₹5,050.00 | ₹631.25 |
Rate build-up
| TOTAL | ₹1,818.33 |
| Add 1% water charges | ₹18.18 |
| TOTAL | ₹1,836.51 |
| Add GST on "X" (multiplying factor 0.2127) | ₹390.63 |
| TOTAL | ₹2,227.14 |
| Add 15% CPOH on "Y" | ₹334.07 |
| TOTAL | ₹2,561.21 |
| Add Cess @1% on "Z" | ₹25.61 |
| Cost of 9 sqm | ₹2,586.82 |
| Cost of 1 sqm | ₹287.42 |
| Say | ₹287.40 |