Filling of empty cavities (as shown in the structural design drawing) with quarry dust mixed with 5% cement (by volume). After initial infill of 50 mm thick with M25 concrete at base/bottom of cavities to seal off, infill wall panel cavities in 3 stages as detailed below, (i) 1st pour / infill to be limited to 0.3 to 0.50 m height from bottom of the panel. (ii) 2nd Pour/ infill: infilling shall be done only after 90 minutes interval between successive pours. The maximum height of infill shall be restricted to 1.5m height or up to the top level of door / window. (iii) 3rd pour/infill: After an interval of 90 minutes of second pour, infill or pour the balance height up to the bottom of embedded RCC tie beam. Pour enough water just required to dampen the dry mix enough to form cake form after each stage. (cost of laying M25 concrete shall be paid separately) (If any rain falls in between any stages of concrete pour, make sure to cover the panel top to prevent ingress of water or water falling into the cavities. In case of water collection over the concrete inside the panel, drill 10mm hole in GFRG panel immediately above concrete filled level to drain out water before pour/in-fill of balance concreting)

Published rate₹2,604.30per cum
Rate analysis

Filling of empty cavities (as shown in the structural design drawing) with quarry dust mixed with 5% cement (by volume). After initial infill of 50 mm thick with M25 concrete at base/bottom of cavities to seal off, infill wall panel cavities in 3 stages as detailed below,

DSR rate₹2,604.30per cum

(i) 1st pour / infill to be limited to 0.3 to 0.50 m height from bottom of the panel.

(ii) 2nd Pour/ infill: infilling shall be done only after 90 minutes interval between successive pours. The maximum height of infill shall be restricted to 1.5m height or up to the top level of door / window.

(iii) 3rd pour/infill: After an interval of 90 minutes of second pour, infill or pour the balance height up to the bottom of embedded RCC tie beam. Pour enough water just required to dampen the dry mix enough to form cake form after each stage.

(cost of laying M25 concrete shall be paid separately)

(If any rain falls in between any stages of concrete pour, make sure to cover the panel top to prevent ingress of water or water falling into the cavities. In case of water collection over the concrete inside the panel, drill 10mm hole in GFRG panel immediately above concrete filled level to drain out water before pour/in-fill of balance concreting)

Item code
26.53
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
cum
Source row
2777

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for filling one panel size 9 sqm (3mx3m Wall)
MATERIAL
1159 Stone dust/Quarry dust filling in cavities of size 230x94 mm cum 0.85 ₹1,100.00 ₹935.00
0367 OPC Cement @ 5% volume of quarry dust tonne 0.061 ₹5,156.00 ₹314.52
Tools and plants hire charges
0002 Mixer hire charges day 0.125 ₹900.00 ₹112.50
LABOUR
0124 Mason 2nd class day 0.125 ₹816.00 ₹102.00
0114 Beldar day 0.125 ₹736.00 ₹92.00

Rate build-up

TOTAL ₹1,556.02
Add 1% water charges ₹15.56
TOTAL ₹1,571.58
Add GST on "X" (multiplying factor 0.2127) ₹334.28
TOTAL ₹1,905.86
Add 15% CPOH on "Y" ₹285.88
TOTAL ₹2,191.74
Add Cess @1% on "Z" ₹21.92
Cost of 0.85 cum ₹2,213.66
Cost of 1 cum ₹2,604.31
Say ₹2,604.30