DSR 2023 · SH 23 · RAIN WATER HARVESTING &

CPWD DSR item 23.9 rate analysis

Providing and fixing factory made precast RCC perforated drain covers, having concrete of strength not less than M-25, of size 1000 x 450x50 mm, reinforced with 8 mm dia four nos longitudinal & 9 nos cross sectional T.M.T. hoop bars, including providing 50 mm dia perforations @ 100 to 125 mm c/c, including providing edge binding with M.S. flats of size 50 mm x 1.6 mm complete, all as per direction of Engineer-in-charge.

Published rate₹1,399.95per No
Rate analysis

Providing and fixing factory made precast RCC perforated drain covers, having concrete of strength not less than M-25, of size 1000 x 450x50 mm, reinforced with 8 mm dia four nos longitudinal & 9 nos cross sectional T.M.T. hoop bars, including providing 50 mm dia perforations @ 100 to 125 mm c/c, including providing edge binding with M.S. flats of size 50 mm x 1.6 mm complete, all as per direction of Engineer-in-charge.

DSR rate₹1,399.95per No
Item code
23.9
Sub-head
SH 23 · RAIN WATER HARVESTING &
Unit
No
Source row
596

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 No. RCC drain cover
MATERIAL
7762 Precast R.C.C. perforated slab each 1 ₹950.00 ₹950.00
LABOUR
9988 Carriage and fixing charges L.S. 15 ₹2.27 ₹34.05

Rate build-up

TOTAL ₹984.05
Add 1 % Water charges on "W" ₹9.84
TOTAL ₹993.89
Add GST on "X" (multiplying factor 0.2127) ₹211.40
TOTAL ₹1,205.29
Add 15% CPOH on "Y" ₹180.79
TOTAL ₹1,386.08
Add Cess @ 1% on "Z" ₹13.86
Cost of 1 No. ₹1,399.94
Say ₹1,399.95

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook