DSR 2023 · SH 23 · RAIN WATER HARVESTING &

CPWD DSR item 23.8 rate analysis

Gravel packing in tubewell construction in accordance with IS: 4097, including providing gravel fine/ medium/ coarse, in required grading & sizes as per actual requirement, all complete as per direction of Engineer-in-charge.

Published rate₹2,024.50per Cum
Rate analysis

Gravel packing in tubewell construction in accordance with IS: 4097, including providing gravel fine/ medium/ coarse, in required grading & sizes as per actual requirement, all complete as per direction of Engineer-in-charge.

DSR rate₹2,024.50per Cum
Item code
23.8
Sub-head
SH 23 · RAIN WATER HARVESTING &
Unit
Cum
Source row
576

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
7772 Pea Gravel cum 1 ₹1,200.00 ₹1,200.00
including carriage
LABOUR
0114 Beldar day 0.3 ₹736.00 ₹220.80
9999 Sundries L.S. 1 ₹2.27 ₹2.27

Rate build-up

TOTAL ₹1,423.07
Add 1 % Water charges on "W" ₹14.23
TOTAL ₹1,437.30
Add GST on "X" (multiplying factor 0.2127) ₹305.71
TOTAL ₹1,743.01
Add 15% CPOH on "Y" ₹261.45
TOTAL ₹2,004.46
Add Cess @ 1% on "Z" ₹20.04
Cost of 1 Cum. ₹2,024.50
Say ₹2,024.50