Supplying, filling, spreading & leveling coarse sand of size range 1.5 mm to 2 mm in recharge pit, in required thickness over gravel layer, for all leads & lifts, all complete as per direction of Engineer -in-charge.

Published rate₹1,538.25per Cum
Rate analysis

Supplying, filling, spreading & leveling coarse sand of size range 1.5 mm to 2 mm in recharge pit, in required thickness over gravel layer, for all leads & lifts, all complete as per direction of Engineer -in-charge.

DSR rate₹1,538.25per Cum
Item code
23.7
Sub-head
SH 23 · RAIN WATER HARVESTING &
Unit
Cum
Source row
556

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
7755 Gravel 1.5 mm to 2 mm cum 1 ₹895.00 ₹895.00
including carriage
LABOUR
0114 Beldar day 0.25 ₹736.00 ₹184.00
9999 Sundries L.S. 1 ₹2.27 ₹2.27

Rate build-up

TOTAL ₹1,081.27
Add 1 % Water charges on "W" ₹10.81
TOTAL ₹1,092.08
Add GST on "X" (multiplying factor 0.2127) ₹232.29
TOTAL ₹1,324.37
Add 15% CPOH on "Y" ₹198.66
TOTAL ₹1,523.03
Add Cess @ 1% on "Z" ₹15.23
Cost of 1 Cum. ₹1,538.26
Say ₹1,538.25

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook