Rate analysis
Supplying, filling, spreading & leveling gravels of size range 5 mm to 10 mm, in the recharge pit, over the existing layer of boulders, in required thickness, for all leads & lifts, all complete as per direction of Engineer-in-charge.
DSR rate₹1,538.25per Cum
- Item code
- 23.6
- Sub-head
- SH 23 · RAIN WATER HARVESTING &
- Unit
- Cum
- Source row
- 536
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 7754 | Gravel 5 mm to 10 mm | cum | 1 | ₹895.00 | ₹895.00 |
| including carriage | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.25 | ₹736.00 | ₹184.00 |
| 9999 | Sundries | L.S. | 1 | ₹2.27 | ₹2.27 |
Rate build-up
| TOTAL | ₹1,081.27 |
| Add 1 % Water charges on "W" | ₹10.81 |
| TOTAL | ₹1,092.08 |
| Add GST on "X" (multiplying factor 0.2127) | ₹232.29 |
| TOTAL | ₹1,324.37 |
| Add 15% CPOH on "Y" | ₹198.66 |
| TOTAL | ₹1,523.03 |
| Add Cess @ 1% on "Z" | ₹15.23 |
| Cost of 1 Cum. | ₹1,538.26 |
| Say | ₹1,538.25 |