DSR 2023 · SH 23 · RAIN WATER HARVESTING &

CPWD DSR item 23.5 rate analysis

Supplying, filling, spreading & leveling stone boulders of size range 5 cm to 20 cm, in recharge pit, in the required thickness, for all leads & lifts, all complete as per direction of Engineer-in-charge.

Published rate₹1,509.80per Cum
Rate analysis

Supplying, filling, spreading & leveling stone boulders of size range 5 cm to 20 cm, in recharge pit, in the required thickness, for all leads & lifts, all complete as per direction of Engineer-in-charge.

DSR rate₹1,509.80per Cum
Item code
23.5
Sub-head
SH 23 · RAIN WATER HARVESTING &
Unit
Cum
Source row
515

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
7753 Boulder 50 mm to 200 mm cum 1 ₹875.00 ₹875.00
including carriage
LABOUR
0114 Beldar day 0.25 ₹736.00 ₹184.00
9999 Sundries L.S. 1 ₹2.27 ₹2.27

Rate build-up

TOTAL ₹1,061.27
Add 1 % Water charges on "W" ₹10.61
TOTAL ₹1,071.88
Add GST on "X" (multiplying factor 0.2127) ₹227.99
TOTAL ₹1,299.87
Add 15% CPOH on "Y" ₹194.98
TOTAL ₹1,494.85
Add Cess @ 1% on "Z" ₹14.95
Cost of 1 Cum. ₹1,509.80
Say ₹1,509.80