Rate analysis
Supplying, filling, spreading & leveling stone boulders of size range 5 cm to 20 cm, in recharge pit, in the required thickness, for all leads & lifts, all complete as per direction of Engineer-in-charge.
DSR rate₹1,509.80per Cum
- Item code
- 23.5
- Sub-head
- SH 23 · RAIN WATER HARVESTING &
- Unit
- Cum
- Source row
- 515
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 7753 | Boulder 50 mm to 200 mm | cum | 1 | ₹875.00 | ₹875.00 |
| including carriage | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.25 | ₹736.00 | ₹184.00 |
| 9999 | Sundries | L.S. | 1 | ₹2.27 | ₹2.27 |
Rate build-up
| TOTAL | ₹1,061.27 |
| Add 1 % Water charges on "W" | ₹10.61 |
| TOTAL | ₹1,071.88 |
| Add GST on "X" (multiplying factor 0.2127) | ₹227.99 |
| TOTAL | ₹1,299.87 |
| Add 15% CPOH on "Y" | ₹194.98 |
| TOTAL | ₹1,494.85 |
| Add Cess @ 1% on "Z" | ₹14.95 |
| Cost of 1 Cum. | ₹1,509.80 |
| Say | ₹1,509.80 |