DSR 2023 · SH 23 · RAIN WATER HARVESTING &

CPWD DSR item 23.4.3 rate analysis

Supplying, assembling, lowering and fixing in vertical position in bore well unplasticized PVC medium well screen (RMS) pipes with ribs, conforming to IS: 12818, including hire & labour charges, fittings & accessories etc. all complete, for all depths, as per direction of Engineer-in-charge. 200 mm nominal size dia

Published rate₹1,255.70per metre
Rate analysis

Supplying, assembling, lowering and fixing in vertical position in bore well unplasticized PVC medium well screen (RMS) pipes with ribs, conforming to IS: 12818, including hire & labour charges, fittings & accessories etc. all complete, for all depths, as per direction of Engineer-in-charge.

DSR rate₹1,255.70per metre

200 mm nominal size dia

Item code
23.4.3
Sub-head
SH 23 · RAIN WATER HARVESTING &
Unit
metre
Source row
442

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 metres
MATERIAL
7752 uPVC slotted pipe 200 mm dia as per IS: 12818 metre 100 ₹875.00 ₹87,500.00
2322 Carriage of Spun iron S & S pipes 200 mm dia 100 metre 0.5 ₹0.00 ₹0.00
Qty = 50 to consider 50% of carriage as per 2321
LABOUR
for lowering
0114 Beldar day 0.5 ₹736.00 ₹368.00
0115 Coolie day 0.5 ₹736.00 ₹368.00
9999 Sundries (Adhesive etc.) L.S. 13.42 ₹2.27 ₹30.46

Rate build-up

TOTAL ₹88,266.46
Add 1 % Water charges on "W" ₹882.66
TOTAL ₹89,149.12
Add GST on "X" (multiplying factor 0.2127) ₹18,962.02
TOTAL ₹1,08,111.14
Add 15% CPOH on "Y" ₹16,216.67
TOTAL ₹1,24,327.81
Add Cess @ 1% on "Z" ₹1,243.28
Cost of 100 metres ₹1,25,571.09
Cost of 1 metre ₹1,255.71
Say ₹1,255.70