CodeDescriptionUnitQuantityRateAmount
Details of cost for 30 metre
MATERIAL
7757 M.S. pipe 100 mm dia casing pipe metre 30 ₹850.00 ₹25,500.00
7764 M.S. socket 100 mm dia each 5 ₹140.00 ₹700.00
2343 Carriage of ductile iron pipes (k7) 100 mm dia 100 metre 0.3 ₹0.00 ₹0.00
including loading and unloading Painting with anticorrosive Paint 3.14 x.0110x30.00=10.36 sqm.
13.65.1 Rate as per Item No.13.65.1 of SH: Finishing sqm 10.36 ₹140.25 ₹1,452.99
LABOUR
0114 Beldar day 1.35 ₹736.00 ₹993.60
0130 Mistry day 0.5 ₹897.00 ₹448.50

Rate build-up

TOTAL ₹29,095.09
Add 1 % Water charges on "W-A" ₹276.42
TOTAL ₹29,371.51
Add GST on "X-A" (multiplying factor 0.2127) ₹5,938.27
TOTAL ₹35,309.78
Add 15% CPOH on "Y-A" ₹5,078.52
TOTAL ₹40,388.30
Add Cess @ 1% on "Z-A" ₹389.35
Cost for 30 metre ₹40,777.65
Cost of 1 metre ₹1,359.26
Say ₹1,359.25