Rate analysis
100 mm nominal size dia having minimum wall thickness 5.00 mm
DSR rate₹1,359.25per metre
- Item code
- 23.10.1
- Sub-head
- SH 23 · RAIN WATER HARVESTING &
- Unit
- metre
- Source row
- 615
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 30 metre | |||||
| MATERIAL | |||||
| 7757 | M.S. pipe 100 mm dia casing pipe | metre | 30 | ₹850.00 | ₹25,500.00 |
| 7764 | M.S. socket 100 mm dia | each | 5 | ₹140.00 | ₹700.00 |
| 2343 | Carriage of ductile iron pipes (k7) 100 mm dia | 100 metre | 0.3 | ₹0.00 | ₹0.00 |
| including loading and unloading Painting with anticorrosive Paint 3.14 x.0110x30.00=10.36 sqm. | |||||
| 13.65.1 | Rate as per Item No.13.65.1 of SH: Finishing | sqm | 10.36 | ₹140.25 | ₹1,452.99 |
| LABOUR | |||||
| 0114 | Beldar | day | 1.35 | ₹736.00 | ₹993.60 |
| 0130 | Mistry | day | 0.5 | ₹897.00 | ₹448.50 |
Rate build-up
| TOTAL | ₹29,095.09 |
| Add 1 % Water charges on "W-A" | ₹276.42 |
| TOTAL | ₹29,371.51 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹5,938.27 |
| TOTAL | ₹35,309.78 |
| Add 15% CPOH on "Y-A" | ₹5,078.52 |
| TOTAL | ₹40,388.30 |
| Add Cess @ 1% on "Z-A" | ₹389.35 |
| Cost for 30 metre | ₹40,777.65 |
| Cost of 1 metre | ₹1,359.26 |
| Say | ₹1,359.25 |