DSR 2023 · SH 22 · WATER PROOFING

CPWD DSR item 22.4.2 rate analysis

Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete : Dumb bell with central bulb (180 mm wide, 8 mm thick)

Published rate₹267.90DSR 2023
Rate analysis

Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete :

DSR rate₹267.90as per item analysis

Dumb bell with central bulb (180 mm wide, 8 mm thick)

Item code
22.4.2
Sub-head
SH 22 · WATER PROOFING
Unit
See analysis
Source row
156

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 metres
MATERIAL
7428 Water stops Dumb bell with central bulb metre 100 ₹173.00 ₹17,300.00
LABOUR
0114 Beldar day 2 ₹736.00 ₹1,472.00
9999 Sundries & wire etc. L.S. 26 ₹2.27 ₹59.02

Rate build-up

TOTAL ₹18,831.02
Add 1 % Water charges on "W" ₹188.31
TOTAL ₹19,019.33
Add GST on "X" (multiplying factor 0.2127) ₹4,045.41
TOTAL ₹23,064.74
Add 15% CPOH on "Y" ₹3,459.71
TOTAL ₹26,524.45
Add Cess @ 1% on "Z" ₹265.24
Cost for 100 metres ₹26,789.69
Cost for 1 metre ₹267.90
Say ₹267.90