DSR 2023 · SH 22 · WATER PROOFING

CPWD DSR item 22.4.1 rate analysis

Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete : Serrated with central bulb (225 mm wide, 8-11 mm thick)

Published rate₹327.65DSR 2023
Rate analysis

Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete :

DSR rate₹327.65as per item analysis

Serrated with central bulb (225 mm wide, 8-11 mm thick)

Item code
22.4.1
Sub-head
SH 22 · WATER PROOFING
Unit
See analysis
Source row
156

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 metres
MATERIAL
7427 Water stops Serrated with central bulb (225 mm wide, 8-11 mm thick) metre 100 ₹215.00 ₹21,500.00
LABOUR
0114 Beldar day 2 ₹736.00 ₹1,472.00
9999 Sundries & wire etc. L.S. 26 ₹2.27 ₹59.02

Rate build-up

TOTAL ₹23,031.02
Add 1 % Water charges on "W" ₹230.31
TOTAL ₹23,261.33
Add GST on "X" (multiplying factor 0.2127) ₹4,947.68
TOTAL ₹28,209.01
Add 15% CPOH on "Y" ₹4,231.35
TOTAL ₹32,440.36
Add Cess @ 1% on "Z" ₹324.40
Cost for 100 metres ₹32,764.76
Cost for 1 metre ₹327.65
Say ₹327.65

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook