Providing and laying water proofing treatment to vertical and horizontal surfaces of depressed portions of W.C., kitchen and the like consisting of: (i) Ist course of applying cement slurry @ 4.4 kg/sqm mixed with water proofing compound conforming to IS 2645 in recommended proportions including rounding off junction of vertical and horizontal surface. (ii) IInd course of 20 mm cement plaster 1:3 (1 cement : 3 coarse sand) mixed with water proofing compound in recommended proportion including rounding off junction of vertical and horizontal surface. (iii) IIIrd course of applying blown or residual bitumen applied hot at 1.7 kg. per sqm of area. (iv) IVth course of 400 micron thick PVC sheet. (Overlaps at joints of PVC sheet should be 100 mm wide and pasted to each other with bitumen @ 1.7 kg/sqm).
Published rate₹769.60DSR 2023
Rate analysis
Providing and laying water proofing treatment to vertical and horizontal surfaces of depressed portions of W.C., kitchen and the like consisting of: (i) Ist course of applying cement slurry @ 4.4 kg/sqm mixed with water proofing compound conforming to IS 2645 in recommended proportions including rounding off junction of vertical and horizontal surface. (ii) IInd course of 20 mm cement plaster 1:3 (1 cement : 3 coarse sand) mixed with water proofing compound in recommended proportion including rounding off junction of vertical and horizontal surface. (iii) IIIrd course of applying blown or residual bitumen applied hot at 1.7 kg. per sqm of area. (iv) IVth course of 400 micron thick PVC sheet. (Overlaps at joints of PVC sheet should be 100 mm wide and pasted to each other with bitumen @ 1.7 kg/sqm).
DSR rate₹769.60as per item analysis
Item code
22.3
Sub-head
SH 22 · WATER PROOFING
Unit
See analysis
Source row
111
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for 10 sqm
MATERIAL
Cement slurry @ 4.4 kg/sqm = 44.00 kg or 0.044 t
0367
Portland Cement (OPC-43 grade)
tonne
0.044
₹5,156.00
₹226.86
2209
Carriage of Cement
tonne
0.044
₹0.00
₹0.00
MATERIAL
Cement plaster 1:3 (20 mm thick)
3.8
Rate as per Item No.3.8 of SH: MORTARS
cum
0.224
₹4,881.95
₹1,093.56
LABOUR
0155
Mason (average)
day
0.94
₹857.00
₹805.58
0115
Coolie
day
1.02
₹736.00
₹750.72
0101
Bhisti
day
1.1
₹816.00
₹897.60
9999
Scafolding and sundries
L.S.
12.61
₹2.27
₹28.62
0313
Blown type petroleum bitumen of penetration 85/25 of approved quality
tonne
0.018
₹38,250.00
₹688.50
10x1.70= 17 kg+ 5% for overlaps of pvc sheet and wastage = 0.018 t
2211
Carriage of Tar bitumen
tonne
0.018
₹0.00
₹0.00
3002
Polyvinyle chloride sheet 400 micron thick i/c 5% for overlaps
sqm
10.5
₹47.00
₹493.50
9977
CARRIAGE
L.S.
13
₹2.27
₹29.51
1213
Water proofing materials@0.10 kg per 50 kg of cement used
kilogram
0.32
₹45.00
₹14.40
Cement slurry = 44 kg
Cement plaster 1:3=5.1x100x0.224=114.24 kg
Total = 158.24 kg = 3.16 Bags of 50 kg of cement
LABOUR for Bitumen coat and laying pvc sheet
0131
Painter
day
0.2
₹816.00
₹163.20
0114
Beldar
day
0.2
₹736.00
₹147.20
0130
Mistry
day
0.06
₹897.00
₹53.82
9999
Sundries
L.S.
7.28
₹2.27
₹16.53
Rate build-up
TOTAL
₹5,409.60
Add 1 % Water charges on "W"
₹54.10
TOTAL
₹5,463.70
Add GST on "X" (multiplying factor 0.2127)
₹1,162.13
TOTAL
₹6,625.83
Add 15% CPOH on "Y"
₹993.87
TOTAL
₹7,619.70
Add Cess @ 1% on "Z"
₹76.20
Cost for 10 sqm
₹7,695.90
Cost for 1 sqm
₹769.59
Say
₹769.60
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.