DSR 2023 · SH 22 · WATER PROOFING

CPWD DSR item 22.25.1 rate analysis

Providing and applying crystalline mortar by mixing in the ratio of 4.5 : 1 (4.5 parts crystalline mortar : 1 part water) for the treatment of faulty construction joints, cracks, tie rod holes and spalled & honeycombed surface of RCC underground structures like basement, water tanks, bridge deck etc. to ensure water tightness. The crystallie mortar shall conform to the EN 1504-3 having compressive strength Class R4 ≥45 MPa and adhesive bond strength Class R3 ≥1.5 MPa. The work shall be carried out all complete as per specification and the direction of the Engineer-In-Charge. The product performance shall carry guarantee for 10 years against any leakage. For sealing cracks and faulty construction joints, routed out/making U-shape groove size 25x25mm and then primed the area with integral crystalline slurry @0.05kg/running metre and while the surface is tacky filled the groove upto surface with crystalline mortar @1.50kg/running metre. Once crystalline mortar is touch dry then finally applied two coats of integral crystalline slurry @0.05kg/running metre per coat.

Published rate₹547.70DSR 2023
Rate analysis

Providing and applying crystalline mortar by mixing in the ratio of 4.5 : 1 (4.5 parts crystalline mortar : 1 part water) for the treatment of faulty construction joints, cracks, tie rod holes and spalled & honeycombed surface of RCC underground structures like basement, water tanks, bridge deck etc. to ensure water tightness. The crystallie mortar shall conform to the EN 1504-3 having compressive strength Class R4 ≥45 MPa and adhesive bond strength Class R3 ≥1.5 MPa. The work shall be carried out all complete as per specification and the direction of the Engineer-In-Charge. The product performance shall carry guarantee for 10 years against any leakage.

DSR rate₹547.70as per item analysis

For sealing cracks and faulty construction joints, routed out/making U-shape groove size 25x25mm and then primed the area with integral crystalline slurry @0.05kg/running metre and while the surface is tacky filled the groove upto surface with crystalline mortar @1.50kg/running metre. Once crystalline mortar is touch dry then finally applied two coats of integral crystalline slurry @0.05kg/running metre per coat.

Item code
22.25.1
Sub-head
SH 22 · WATER PROOFING
Unit
See analysis
Source row
788

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1.00 meter
MATERIAL :
0353 Crystalline Mortar @1.50 kg per meter kilogram 1.5 ₹209.00 ₹313.50
0351 Integral crystalline slurry for priming and finishing kilogram 0.15 ₹214.00 ₹32.10
(3 x 0.05kg / meter) = 0.15kg
LABOUR
9999 For making crystalline mortar and repair work etc.. L.S. 14.45 ₹2.27 ₹32.80
9999 Sundries L.S. 1.15 ₹2.27 ₹2.61
9999 Carriage of material and tools cost etc.. L.S. 1.75 ₹2.27 ₹3.97

Rate build-up

TOTAL ₹384.98
Add 1 % Water charges on "W" ₹3.85
TOTAL ₹388.83
Add GST on "X" (multiplying factor 0.2127) ₹82.70
TOTAL ₹471.53
Add 15% CPOH on "Y" ₹70.73
TOTAL ₹542.26
Add Cess @ 1% on "Z" ₹5.42
Cost for 1.00 meter ₹547.68
Say ₹547.70