DSR 2023 · SH 22 · WATER PROOFING

CPWD DSR item 22.24A rate analysis

Providing & Applying high quality acrylic modified resin based texture of Dholpur/Red sand stone Pattern with anti algae and UV resistance properties to be applied as intermediate finish in desired pattern @ 43.04 kgs/10 sqm to form film of 1- 1.5 mm thickness after scrapping and properly cleaning the surface to remove loose particles from the plaster surface, followed by top coating with Premium Acrylic Smooth exterior paint with Silicone additives of required shade by two or more coats @ 1.43 litres/10 sqm, complete as the direction of Engineer -in-Charge.

Published rate₹597.00per sqm
Rate analysis

Providing & Applying high quality acrylic modified resin based texture of Dholpur/Red sand stone Pattern with anti algae and UV resistance properties to be applied as intermediate finish in desired pattern @ 43.04 kgs/10 sqm to form film of 1- 1.5 mm thickness after scrapping and properly cleaning the surface to remove loose particles from the plaster surface, followed by top coating with Premium Acrylic Smooth exterior paint with Silicone additives of required shade by two or more coats @ 1.43 litres/10 sqm, complete as the direction of Engineer -in-Charge.

DSR rate₹597.00per sqm
Item code
22.24A
Sub-head
SH 22 · WATER PROOFING
Unit
sqm
Source row
762

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 Sqm
MATERIAL
8513 Acrylic modified resin based texture kg 45.19 ₹50.00 ₹2,259.50
43.04 kg + 2.15 (Add wastage 5%) = 45.19 kg
Quantity taken for cost using once = 10 sqm
Top coat with premium acrylic exterior paint (two or more coats)
13.112.1 Rate as per Item No.13.112.1 of SH:Finishing sqm 10 ₹131.30 ₹1,313.00
9977 Carriage of materials L.S. 3.9 ₹2.27 ₹8.85
LABOUR
0115 Coolie day 0.56 ₹736.00 ₹412.16
0123 Mason 1st class day 0.56 ₹897.00 ₹502.32
9999 Sundries and scaffolding L.S. 40 ₹2.27 ₹90.80

Rate build-up

TOTAL ₹4,586.63
Add 1 % Water charges on "W-A" ₹32.74
TOTAL ₹4,619.37
Add GST on "X-A" (multiplying factor 0.2127) ₹703.26
TOTAL ₹5,322.63
Add 15% CPOH on "Y-A" ₹601.44
TOTAL ₹5,924.07
Add Cess @ 1% on "Z-A" ₹46.11
Cost of 10 sqm ₹5,970.18
Cost of 1 sqm ₹597.02
Say ₹597.00