DSR 2023 · SH 22 · WATER PROOFING

CPWD DSR item 22.24 rate analysis

Providing and applying integral crystalline (dry shake) of hydrophilic in nature for waterproofing treatment to the RCC structures like basement raft, foundation slab, sewage & water treatment plant slab, warehouses floor, parking structures and water tank base slab etc. sprinkled @0.60kg per sqm or higher as recommended by the manufacturer's specification over the lean concrete of above cited structures. The material shall meet the requirements as specified in ACI-212-3R-2010 i.e. by reducing permeability of concrete by more than 85%, compared control concrete as per DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The crystalline dry-shake shall be capable of self-healing of cracks up to a width of 0.50mm. The work shall be carried out all complete as per specification and the direction of the Engineer-in-charge. The product performance shall carry guarantee for 10 years against any leakage.

Published rate₹309.60DSR 2023
Rate analysis

Providing and applying integral crystalline (dry shake) of hydrophilic in nature for waterproofing treatment to the RCC structures like basement raft, foundation slab, sewage & water treatment plant slab, warehouses floor, parking structures and water tank base slab etc. sprinkled @0.60kg per sqm or higher as recommended by the manufacturer's specification over the lean concrete of above cited structures. The material shall meet the requirements as specified in ACI-212-3R-2010 i.e. by reducing permeability of concrete by more than 85%, compared control concrete as per DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The crystalline dry-shake shall be capable of self-healing of cracks up to a width of 0.50mm. The work shall be carried out all complete as per specification and the direction of the Engineer-in-charge. The product performance shall carry guarantee for 10 years against any leakage.

DSR rate₹309.60as per item analysis
Item code
22.24
Sub-head
SH 22 · WATER PROOFING
Unit
See analysis
Source row
742

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 sqm
MATERIAL :
0354 Integral crystalline dry shake kilogram 0.6 ₹308.00 ₹184.80
LABOUR
9999 For measuring and sprinkling of waterproofing material L.S. 11.55 ₹2.27 ₹26.22
9999 Sundries L.S. 1.15 ₹2.27 ₹2.61
9999 Carriage of material and tools cost etc.. L.S. 1.75 ₹2.27 ₹3.97

Rate build-up

TOTAL ₹217.60
Add 1 % Water charges on "W" ₹2.18
TOTAL ₹219.78
Add GST on "X" (multiplying factor 0.2127) ₹46.75
TOTAL ₹266.53
Add 15% CPOH on "Y" ₹39.98
TOTAL ₹306.51
Add Cess @ 1% on "Z" ₹3.07
Cost for 1.00 sqm ₹309.58
Say ₹309.60

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook