DSR 2023 · SH 22 · WATER PROOFING

CPWD DSR item 22.25.2 rate analysis

Providing and applying crystalline mortar by mixing in the ratio of 4.5 : 1 (4.5 parts crystalline mortar : 1 part water) for the treatment of faulty construction joints, cracks, tie rod holes and spalled & honeycombed surface of RCC underground structures like basement, water tanks, bridge deck etc. to ensure water tightness. The crystallie mortar shall conform to the EN 1504-3 having compressive strength Class R4 ≥45 MPa and adhesive bond strength Class R3 ≥1.5 MPa. The work shall be carried out all complete as per specification and the direction of the Engineer-In-Charge. The product performance shall carry guarantee for 10 years against any leakage. For patching of tie rod holes, prepared tie rod hole surface and then primed the area with integral crystalline slurry @0.070kg/sqm and while the surface is tacky repair and then filled the tie rod holes with crystalline mortar@0.040kg per hole. The crystalline mortar should be tightly rodded into tie rod holes or packed tightly (For 25x25x25 mm tie rod hole, use 0.040kg to fill the hole)

Published rate₹23.05DSR 2023
Rate analysis

Providing and applying crystalline mortar by mixing in the ratio of 4.5 : 1 (4.5 parts crystalline mortar : 1 part water) for the treatment of faulty construction joints, cracks, tie rod holes and spalled & honeycombed surface of RCC underground structures like basement, water tanks, bridge deck etc. to ensure water tightness. The crystallie mortar shall conform to the EN 1504-3 having compressive strength Class R4 ≥45 MPa and adhesive bond strength Class R3 ≥1.5 MPa. The work shall be carried out all complete as per specification and the direction of the Engineer-In-Charge. The product performance shall carry guarantee for 10 years against any leakage.

DSR rate₹23.05as per item analysis

For patching of tie rod holes, prepared tie rod hole surface and then primed the area with integral crystalline slurry @0.070kg/sqm and while the surface is tacky repair and then filled the tie rod holes with crystalline mortar@0.040kg per hole. The crystalline mortar should be tightly rodded into tie rod holes or packed tightly (For 25x25x25 mm tie rod hole, use 0.040kg to fill the hole)

Item code
22.25.2
Sub-head
SH 22 · WATER PROOFING
Unit
See analysis
Source row
788

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 no. hole
MATERIAL :
0353 Crystalline mortar@0.040 kg per hole kilogram 0.04 ₹209.00 ₹8.36
LABOUR
9999 For making crystalline mortar and repair work etc.. L.S. 2.9 ₹2.27 ₹6.58
9999 Sundries L.S. 0.3 ₹2.27 ₹0.68
9999 Carriage of material and tools cost etc.. L.S. 0.25 ₹2.27 ₹0.57

Rate build-up

TOTAL ₹16.19
Add 1 % Water charges on "W" ₹0.16
TOTAL ₹16.35
Add GST on "X" (multiplying factor 0.2127) ₹3.48
TOTAL ₹19.83
Add 15% CPOH on "Y" ₹2.97
TOTAL ₹22.80
Add Cess @ 1% on "Z" ₹0.23
Cost for each hole ₹23.03
Say ₹23.05